INSP-Final Inspection | 11/4/2004 | 11/4/2004 | 11/4/2004 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled
|
INSP-Final Inspection | 11/1/2004 | 11/1/2004 | 11/1/2004 | A | FAIL |
Troy Cobbley
|
|
|
Certify backflow preventer and new sprinkler system
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2004 | 10/7/2004 | 10/7/2004 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed 10/6/2004 12:22:06 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2004 | 10/5/2004 | 10/5/2004 | P | PART |
Troy Cobbley
|
|
|
Underground hydro test passed. Overhead test failed 10/5/2004 4:19:59 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/28/2004 | 9/29/2004 | 9/29/2004 | A | FAIL |
Troy Cobbley
|
|
|
Overhead sprinkler piping was inspected. Offices, riser and FDC not inspected. I found many sprinkler uprights covered with tape, one upright bent, earthquake bracing was missing and retaining straps missing from one side of the trapeze hangers. See approved plans for specific locations. Underground flush was ok and entry was made under FIR04-00384. 9/29/2004 11:10:41 AM
|
INSP-Supply line flush | 9/28/2004 | 9/28/2004 | 9/28/2004 | P | CANC |
Troy Cobbley
|
|
|
contractor did not have valve key so no flush was done 9/28/2004 4:32:46 PM
|