INSP-Final Inspection | 2/3/2005 | 2/4/2005 | 2/4/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled 2/4/2005 9:56:59 AM
|
INSP-Final Inspection | 1/28/2005 | 1/28/2005 | 1/28/2005 | P | FAIL |
Rick Jackson
|
|
|
OH hydro okay; flow switch not working properly - cycles; forward flow of BFP okay 1/28/2005 1:08:42 PM
|
INSP-Sprinkler Rough-in | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | PART |
Rick Jackson
|
|
|
terrry - ###-#### Hydro failed; okay to cover areas identified on plans and resubmittals for beam areas 1/27/2005 10:45:23 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | PART |
Rick Jackson
|
|
|
###-#### - terry Note: please call prior to inspection Hydro failed; okay to cover areas identified on plans and resubmittals for beam areas 1/27/2005 10:45:36 AM
|
INSP-Supply line flush | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 1/26/2005 at 3:34:50 PM. Contact: ###-####. UG has been hydro'd and flushed 1/27/2005 8:16:38 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2004 | 12/21/2004 | 12/21/2004 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed 12/20/2004 3:20:51 PM
|
INSP-Supply line flush | 12/20/2004 | 12/21/2004 | 12/21/2004 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed 12/20/2004 3:21:27 PM
|
INSP-Conference | 12/16/2004 | 12/16/2004 | 12/16/2004 | P | PART |
Troy Cobbley
|
|
|
Sanctuary piping rough-in is ok 12/16/2004 4:09:40 PM
|
INSP-Conference | 12/13/2004 | 12/14/2004 | 12/14/2004 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping in the central corridor is ok to cover 12/14/2004 8:34:40 AM
|
INSP-Sprinkler Rough-in | 12/9/2004 | 12/10/2004 | 12/10/2004 | A | PART |
Troy Cobbley
|
|
|
Combustible concealed spaces as discussed down the main corridor and for the beams over the classrooms need to be filled with non-combustible insulation or add upright sprinklers 12/10/2004 12:10:05 PM
|
INSP-Sprinkler Rough-in | 11/12/2004 | 11/15/2004 | 11/15/2004 | A | CANC |
Troy Cobbley
|
|
|
Per Russ with treasure valley fire 11/15/2004 8:06:08 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2004 | 11/3/2004 | 11/3/2004 | P | PART |
Troy Cobbley
|
|
|
Overhead sprinkler piping in the remodeled classrooms and the new wing is ok. A second inspection will be needed for piping to pendants. There a pipe sizes installed that do not match approved plans as well as pendants installed in areas not shown to have ceilings. Resubmit plans to city of boise for approval showing ceilings and actual pipe sizes 11/3/2004 4:14:13 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2004 | 10/4/2004 | 10/4/2004 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler supply stub-in is ok to bury 10/4/2004 4:34:42 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2004 | 9/22/2004 | 9/22/2004 | P | PART |
Troy Cobbley
|
|
|
Inspection was just for the underground. Piping is ok to bury from the tap to the curbing just outside of the building. 9/22/2004 4:11:44 PM
|