INSP-Final Inspection | 12/7/2004 | 12/7/2004 | 12/7/2004 | P | PASS |
Rick Jackson
|
|
|
UG flush and hydro okay - final okay 12/7/2004 3:38:09 PM
|
INSP-Final Inspection | 10/21/2004 | 10/22/2004 | 10/22/2004 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/21/2004 at 12:49:53 PM. Contact: ###-####. 2 layers of hard foam used over section of UG near steps; okay to cover 10/22/2004 9:40:36 AM
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2004 | 10/1/2004 | 10/1/2004 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/1/2004 at 10:35:42 AM. Contact: ###-####. Will reschedule 10/1/2004 4:14:17 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2004 | 9/27/2004 | 9/27/2004 | P | FAIL |
Rick Jackson
|
|
|
sam; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Resubmit due to changes; depth of bury won't be 4 ft 6 inches at present location 9/27/2004 4:29:28 PM
|