INSP-Final Inspection | 1/18/2006 | 1/19/2006 | 1/19/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 3/8/2005 | 3/9/2005 | 3/9/2005 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed 3/9/2005 4:04:56 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/28/2004 | 10/28/2004 | 10/28/2004 | P | PART |
Troy Cobbley
|
|
|
Ok to finish cover of the fdc. Still need to remove the valve and install the ball drip. 10/28/2004 2:27:36 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2004 | 10/21/2004 | 10/21/2004 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line hydro is passed. Other items as listed on the previous inspection still need to be addressed. 10/21/2004 1:28:15 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2004 | 10/20/2004 | 10/20/2004 | A | FAIL |
Rick Jackson
|
|
|
To verify FDC and vault installation. Re submitted plans are in job trailer.; Phone #: ###-#### Internet Inspection Request from: Trent Bice Need gravel in pit; ball valve will have to be removed after hydro 10/20/2004 11:31:07 AM
|
INSP-Sprinkler Rough-in/Hydro | 10/11/2004 | 10/11/2004 | 10/11/2004 | P | FAIL |
Troy Cobbley
|
|
|
Need approval from bill or dave on modifications to the fire dept. connection location before covering of the pipe 10/11/2004 4:23:33 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/7/2004 | 10/8/2004 | 10/8/2004 | A | PART |
Troy Cobbley
|
|
|
Piping under roadway is ok to cover. Thrust blocks and beding is not done yet. Will verify this afternoon. 10/8/2004 12:27:16 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/7/2004 | 10/8/2004 | 10/8/2004 | P | CANC |
Troy Cobbley
|
|
|
Contractor to call in new inspection when the rest of the underground has been installed. Trent to provide pictures of the thrust block on the 45. 10/8/2004 3:19:36 PM
|