INSP-Final Inspection | 1/21/2005 | 1/21/2005 | 1/21/2005 | P | PASS |
Troy Cobbley
|
|
|
fire sprinklers finaled
|
INSP-Final Inspection | 1/17/2005 | 1/18/2005 | 1/18/2005 | P | FAIL |
Troy Cobbley
|
|
|
Need interconnections with the fire alarm system tested and the 200 degree upright in the riser room replaced with at 155 1/18/2005 3:57:38 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2005 | 1/18/2005 | 1/18/2005 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed 1/18/2005 3:38:36 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/17/2004 | 12/20/2004 | 12/20/2004 | P | PART |
Troy Cobbley
|
|
|
Upright sprinkler head is overspaced under the east stairway. Provide the correct size of hanger rings on the trapeze and resubmit plans showing the steel pipe instead of the plastic and the branchline that was added 12/20/2004 12:04:59 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2004 | 12/15/2004 | 12/15/2004 | P | PART |
Troy Cobbley
|
|
|
Restrooms and riser room is ok to cover 12/15/2004 3:01:40 PM
|
INSP-Supply line flush | 12/15/2004 | 12/15/2004 | 12/15/2004 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line hydro test passed 12/15/2004 3:01:11 PM
|