INSP-Final Inspection | 4/18/2006 | 4/18/2006 | 4/18/2006 | P | PASS |
Forrest France
|
|
|
Corrections have been completed, inspection passed.
|
INSP-Final Inspection | 5/18/2005 | 5/20/2005 | 5/20/2005 | P | PART |
Forrest France
|
|
|
Farmers and Merchants Bank spaces on the basement, first, and second floors passed fire alarm inspection. Revised plans need to reflect additional HS in basement elevator lobby, actual location of heat pump now in men's room, correct cd rating on HS in f
|
INSP-Final Inspection | 2/28/2005 | 3/1/2005 | 3/1/2005 | A | PART |
Troy Cobbley
|
|
|
Temporary occupancy given. Fire alarm panel and NAC panels inspected. Duct detectors on the sixth floor inspected. Induct detectors at main supply and returns on first through sixth floor inspected. Pull stations on all floors inspected. Audio visuals on sixth floor and first floor lobby inspected. Individual a/v's on first through sixth and basement inspected. All sprinkler monitoring points inspected. All other items not inspected. Plans will need to be resubmitted with changes which include ceiling mounted a/v's, deletion of pull on sixth floor, additional heat in penthouse and relocated NAC panels. 3/1/2005 2:53:28 PM
|
INSP-Final Inspection | 2/28/2005 | 2/28/2005 | 2/28/2005 | P | FAIL |
Troy Cobbley
|
|
|
Items tested included annunciation, manual pull stations and induct smoke detectors for common supply/returns for 2nd - 6th floors. Also tested duct smoke detectors on hvac units on 6th floor only. Tested all tamper switches and flow switches for basement through penthouse. Items still needing testing for temporary occupancy are elevator recall for the new elevators, induct detectors on first floor and duct detectors in penthouse and NAC supervision 2/28/2005 4:05:49 PM
|
INSP-Final Inspection | 2/23/2005 | 2/25/2005 | 2/25/2005 | A | FAIL |
Troy Cobbley
|
|
|
terri ###-#### Fire alarm is not ready for inspection. Fire pump controler handle has been broken. Fire pump is in phase reversal (running backwards). Elevator car 2 was not ready for recall testing. No sprinkler heads on second floor. Items tested are phones, battery loss, ac loss, pull stations in basement and first floor, loss of power at pump, pump running and phase reversal. System is not ready for testing. 2/25/2005 2:08:40 PM
|
INSP-Alarm Testing | 2/18/2005 | 2/24/2005 | 2/24/2005 | A | CANC |
Troy Cobbley
|
|
|
terry ###-####
|
INSP-Final Inspection | 2/23/2005 | 2/24/2005 | 2/24/2005 | A | CANC |
Troy Cobbley
|
|
|
terri ###-####
|
INSP-Conference | 2/17/2005 | 2/18/2005 | 2/18/2005 | A | DONE |
|
|
|
Tomlinson is requesting for inspection for the 6th floor occupancy on Thursday 2/24/05. The core and shell permits will NOT be ready to be finaled.
The entire building shall be WET. Spacing and head height in non-occupied and construction areas may be obstructed, hi/low heads are acceptable.
The following shall be completed and tested to allow a partial on the fire alarm inspection:
1) ALL sprinkler monitoring (throughout the building) and fire pump functional
2) Basement: pull stations at all exits. Clear access from the first floor to the riser room and fire pump.
3) 1st floor: all shell and core areas completed.
4) 2nd through 5th: pull stations at all exits. (restrooms need not have notification at this time)
5) The 6th floor complete.
|