INSP-Final Inspection | 1/30/2008 | 1/30/2008 | 1/30/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2006 | 8/9/2006 | 8/10/2006 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed inspection.
|
INSP-Sprinkler Rough-in | 8/7/2006 | 8/7/2006 | 8/7/2006 | P | PART |
Forrest France
|
|
|
Need to perform hydrostatic test, OH installation is acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2005 | 2/11/2005 | 2/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed twice today. I told fitter to hydro test system prior to me being called for test. Next one will be charged a re-inspection fee if it fails. 2/11/2005 3:00:32 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/7/2005 | 2/8/2005 | 2/8/2005 | A | PART |
Troy Cobbley
|
|
|
Hydro test for the 6th floor failed. Hydro test for the 1st floor passed. 2/8/2005 12:38:31 PM
|
INSP-Sprinkler Rough-in | 12/21/2004 | 12/21/2004 | 12/21/2004 | P | PART |
Rick Jackson
|
|
|
Adam; Phone #: ###-#### Internet Inspection Request from: Jan Rice Okay to cover hard lid areas; need as-builts turned in as minor changes have been made due to duct work, etc; the 2 inch has shifted and some branch lines were rerouted 12/21/2004 1:52:35 PM
|