Permit Information
Permit NumberFIR04-00768
StatusFinaled
Name FUTURETECH
Site Address 6325 N CLOVERDALE RD
Project Namealm Springhill Suites/Marriott
Customer Number 
ePlanReview 
Description
To provide a required manual fire alarm system that includes sprinkler monitoring, required automatic detection, HVAC shutdown, fire/smoke damper control, door release, elevator recall/shutdown and notification throughout.

5/12/2005 - Plan Modification. The ICP modules required readdressing to function with the FACP. The drawings have been clouded to indicate the change in addressing on other initiating devices. The PDS Fire Inspector shall field verify for accuracy.

The associated building permit (BLD 04-01267) is to construct a new 66,322 sq.ft. four story, wood framed, 119 unit motel with approximately 7,100 sq.ft. for meeting rooms, indoor spa, lobby area and food prep kitchen and a 1,720 sq.ft. covered porte coochere . NOTE: This building is fully fire sprinklered for area increase. This permit does not include the interior spa, exterior swimming pool, pool equipment and pool equipment building. Separate permits will be required to be obtained prior to construction. All construction per the approved plans and attached comment list. MJP DRH 04-044 CUP 04-00016 Springhill Suites Marriott Hotel
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/16/20055/17/20055/17/2005APASS
DetailsTroy Cobbley
Fire alarm finaled
INSP-Alarm Testing5/13/20055/16/20055/16/2005AFAIL
DetailsTroy Cobbley
Provide signal verification and nfpa 72 record of completion forms.
INSP-Alarm Testing5/5/20055/6/20055/6/2005APART
DetailsTroy Cobbley
Contact: ###-####. See approved plans, sheet 1 for items left to verify.
INSP-Alarm Testing5/4/20055/5/20055/5/2005APART
DetailsTroy Cobbley
Tested initiating devices on the first floor. This includes smokes, pulls and sprinkler devices. Need to test heat detectors, verify ceiling a/v's are listed for ceiling, add a/v in the electrical room and get the addresses straightened out.
INSP-Alarm Testing5/3/20055/4/20055/4/2005APART
DetailsTroy Cobbley
The only items tested today were the battery load and the phone lines which both passed.
INSP-Conference1/7/20051/7/20051/7/2005PDONE
DetailsTroy Cobbley
I was at the job site doing a fire sprinkler rough-in on the 3rd and 4th floors and found fire alarm device backboxes and wire installed throughout the 3rd floor and in small areas of the 4th floor. After verifing that only the 2nd floor had be approved for starting with Mary and Dave I issued a stop work order to the project superintendant. Stop work order is for all fire alarm work and sheet rock work that would cover up the fire alarm work. I made this clear with the superintendant.