INSP-Final Inspection | 6/1/2005 | 6/1/2005 | 6/1/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Final Inspection | 5/23/2005 | 5/23/2005 | 5/23/2005 | P | FAIL |
Forrest France
|
|
|
Q.R.E.C G.B heads in one compartment of bank vault are mixed with a solder link head in the same compartment, verify if response time is the same to meet NFPA 8.3.3.2. Verify if vault area is indeed LH, it appears to be used as storage.
|
INSP-Final Inspection | 5/20/2005 | 5/20/2005 | 5/20/2005 | P | FAIL |
Forrest France
|
|
|
Remove fire sprinkler canopy at front entry first floor that has been used as a coverplate for a previously used hole. Inadequate sprinkler coverage in basement bank vault as installed, heads are overspaced off wall.
|
INSP-Final Inspection | 4/18/2005 | 4/19/2005 | 4/19/2005 | A | FAIL |
Forrest France
|
|
|
2nd floor rough-in fail inspection. Two pendent heads in CEO office are too close to heat diffusers - must be min. one foot away or increase temp. rating. Upright head blocked in open office without ceiling, verify drop ceiling install or correct the
|
INSP-Final Inspection | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | FAIL |
Forrest France
|
|
|
Contact: ###-####. Fail inspection, approved plans not available on site for review.
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2005 | 2/23/2005 | 2/23/2005 | P | PART |
Troy Cobbley
|
|
|
basement hydro test passed. Could not do a rough-in inspection due to plans not matching installation. I spoke to Gerald at Treasure Valley about this. 2/23/2005 2:47:38 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/16/2005 | 2/17/2005 | 2/17/2005 | A | PART |
Troy Cobbley
|
|
|
Second floor rough-in is ok but need armovers inspected when complete. Hardlid areas are ok to cover. Need resubmittals showing piping changes on second floor 2/17/2005 11:26:49 AM
|