Permit Information
Permit NumberFIR04-00811
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 121 N 9TH ST
Project NameSPR FARMER & MERCHANTS B TO 2
Customer Number 
ePlanReview 
Description
(FARMERS & MERCHANTS STATE BANK - SUITES 4B, 100, 200) To add fire sprinkler protection for the remodel a 1,602-ft/2 area in the basement, a 3,398-ft/2 area on the first floor, and the entire 12,085-ft/2 second floor, for a new bank tenant. The fire sprinkler work is related to new interior walls and suspended ceilings and gypsum board soffits and ceilings. This building is required to be fully fire sprinklered. This fire protection work shall comply with the IFC 2000 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD04-01885.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/1/20056/1/20056/1/2005APASS
DetailsForrest France
Fire sprinkler finaled.
INSP-Final Inspection5/23/20055/23/20055/23/2005PFAIL
DetailsForrest France
Q.R.E.C G.B heads in one compartment of bank vault are mixed with a solder link head in the same compartment, verify if response time is the same to meet NFPA 8.3.3.2. Verify if vault area is indeed LH, it appears to be used as storage.
INSP-Final Inspection5/20/20055/20/20055/20/2005PFAIL
DetailsForrest France
Remove fire sprinkler canopy at front entry first floor that has been used as a coverplate for a previously used hole. Inadequate sprinkler coverage in basement bank vault as installed, heads are overspaced off wall.
INSP-Final Inspection4/18/20054/19/20054/19/2005AFAIL
DetailsForrest France
2nd floor rough-in fail inspection. Two pendent heads in CEO office are too close to heat diffusers - must be min. one foot away or increase temp. rating. Upright head blocked in open office without ceiling, verify drop ceiling install or correct the
INSP-Final Inspection4/15/20054/18/20054/18/2005AFAIL
DetailsForrest France
Contact: ###-####. Fail inspection, approved plans not available on site for review.
INSP-Sprinkler Rough-in/Hydro2/22/20052/23/20052/23/2005PPART
DetailsTroy Cobbley
basement hydro test passed. Could not do a rough-in inspection due to plans not matching installation. I spoke to Gerald at Treasure Valley about this. 2/23/2005 2:47:38 PM
INSP-Sprinkler Rough-in/Hydro2/16/20052/17/20052/17/2005APART
DetailsTroy Cobbley
Second floor rough-in is ok but need armovers inspected when complete. Hardlid areas are ok to cover. Need resubmittals showing piping changes on second floor 2/17/2005 11:26:49 AM