INSP-Final Inspection | 12/15/2005 | 12/15/2005 | 12/15/2005 | P | PASS |
Forrest France
|
|
|
Underground fire supply line finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/9/2005 | 12/12/2005 | 12/12/2005 | A | DEFR |
Forrest France
|
|
|
mike Note: 24 hr air test; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles NOTE: Wrong permit number called in, this was meant for FIR05-00385 for the overhead, not under FIR04-00812 for the associated UG supply.
|
INSP-Sprinkler Rough-in | 11/3/2005 | 11/4/2005 | 11/4/2005 | P | PART |
Forrest France
|
|
|
2nd floor corridor hard lid and 1st floor restrooms hard lid are okay to cover for overhead rough-in.
|
INSP-Supply line flush | 8/9/2005 | 8/9/2005 | 8/9/2005 | A | PART |
Forrest France
|
|
|
Two hour hydrostatic test and supply line flush both passed inspection.
|
INSP-Supply line flush | 7/27/2005 | 7/27/2005 | 7/27/2005 | A | FAIL |
Forrest France
|
|
|
Underground fire supply work appears to be installed in a satisfactory manner, however the resubmitted plans and notes with scope of work does not address phase 2 (connection to city supply) work. This work must be submitted and approved prior to field inspection and sign off.
|
INSP-Supply line flush | 1/18/2005 | 1/19/2005 | 1/19/2005 | A | PART |
Rick Jackson
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice UG stub out only - okay; used one piece riser 1/19/2005 10:10:01 AM
|