INSP-Final Inspection | 8/10/2006 | 8/11/2006 | 8/11/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2005 | 2/23/2005 | 2/23/2005 | P | PART |
Troy Cobbley
|
|
|
With Bill Alexander's permission the remodeled restroom fire sprinklers appear ok. Resubmittals will be required before final will be given. 2/24/2005 9:53:07 AM
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2005 | 2/22/2005 | 2/22/2005 | P | CANC |
Troy Cobbley
|
|
|
Tile workers were installing the floor so there is no access at this time. 2/22/2005 4:03:24 PM
|
INSP-Sprinkler Rough-in | 2/11/2005 | 2/11/2005 | 2/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
Floor plan does not match fire sprinkler plans. Piping sizing on plan does not match field. Quick responce and standard responce heads are mixed and different temperatures from listing on plans. Sidewall head too far from ceiling. One pendant not installed yet. Two uprights blocked by new soffits. Inspection stopped. Plans need to be resubmitted. 2/11/2005 4:17:02 PM
|
INSP-Final Inspection | 8/2/2006 | 8/3/2006 | | P | |
Forrest France
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|