INSP-Final Inspection | 1/18/2006 | 1/19/2006 | 1/19/2006 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler permit finaled
|
INSP-Final Inspection | 12/28/2005 | 12/29/2005 | 12/29/2005 | P | FAIL |
Troy Cobbley
|
|
|
Need to do all of the riser inspection including the forward flush. Provide E.Q. on the three sprig ups. Provide the correct connections for the stage hose valves. There is a clearance issue in the storage room. Check ball drip.
|
INSP-Final Inspection | 10/19/2005 | 10/20/2005 | 10/20/2005 | P | FAIL |
Troy Cobbley
|
|
|
Project is not ready for final. Need the latest and greatest plans, canopies missing, taped heads...ect.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2005 | 10/20/2005 | 10/20/2005 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 7/21/2005 | 7/21/2005 | 7/21/2005 | P | PART |
Troy Cobbley
|
|
|
Hanger dificiencies as marked on the last edition of the approved have been corrected but the latest revision of the plans was not on site.
|
INSP-Sprinkler Rough-in | 5/19/2005 | 5/20/2005 | 5/20/2005 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping fo rthe most part is ok. See city approved plans for locations of deficiecies which include missing hangers, modified routing of piping, deletion of heads and additional heads to be required under duct work in the auditorium. Plans will n
|
INSP-Sprinkler Rough-in | 5/3/2005 | 5/3/2005 | 5/3/2005 | P | PART |
Troy Cobbley
|
|
|
Sprinkler piping for room 137 is ok to cover. Looked at the eq bracing for the north half of building. It looks ok.
|