INSP-Final Inspection | 3/10/2006 | 3/13/2006 | 3/13/2006 | A | PASS |
Forrest France
|
|
|
Required items on the correction notice have been completed, shell and core fire alarm permit finaled.
|
INSP-Final Inspection | 2/27/2006 | 2/28/2006 | 2/28/2006 | P | FAIL |
Forrest France
|
|
|
Need to post building map showing roof plan including clock tower, update plans and 1st floor map to show changed EOL location from device 8:8.
|
INSP-Alarm Testing | 11/22/2005 | 11/23/2005 | 11/23/2005 | P | PART |
Forrest France
|
|
|
The north elevator alarm devices tested okay.
|
INSP-Alarm Testing | 11/22/2005 | 11/22/2005 | 11/22/2005 | P | CANC |
Forrest France
|
|
|
|
INSP-Final Inspection | 11/10/2005 | 11/10/2005 | 11/10/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hanniman's permission until resubmittals and elevator are finished and finaled. Elevator is not to be used until inspected.
|
INSP-Alarm Testing | 11/9/2005 | 11/9/2005 | 11/9/2005 | P | PART |
Forrest France
|
|
|
The north elevator remains to be completed and tested, final pending verification of resubmittals for field changes.
|
INSP-Sprinkler Rough-in | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | PART |
Forrest France
|
|
|
North elevator is still non-functional, provide resubmittals for all required changes.
|
INSP-Alarm Testing | 10/24/2005 | 10/25/2005 | 10/25/2005 | P | FAIL |
Forrest France
|
|
|
North elevator is not functional at this time, need an additional SD above the FACP due to a beam pocket obstruction, clock tower AV is not functional, provide signage at FACP room door, outside bell to be relocated at face of brick, elevator roof damper is not required due to barometric shaft, resubmitt for changed EOL, added devices, deleted damper and revised matrix for pump, provide audibility for the FACP room.
|
INSP-Alarm Testing | 10/24/2005 | 10/24/2005 | 10/24/2005 | A | PART |
Forrest France
|
|
|
Partial shell alarm inspection only.
|
INSP-Alarm Testing | 10/21/2005 | 10/21/2005 | 10/21/2005 | P | FAIL |
Forrest France
|
|
|
Lower pull station to 48" AFF, provide additional smoke at the panel due to beam blockage, verify audibility in the FACP room, fire pump run shows as an alarm and the matrix indicates a supervisory, change label at roof tamper and stair flow 108, outside bell shall silence upon waterflow ceasation, all sprinkler alarms tested today, no other items tested at this time.
|