INSP-Final Inspection | 5/23/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Forrest France
|
|
|
Overhead hydrostatic test of spray room supply and branch lines passed inspection.
|
INSP-Final Inspection | 5/20/2005 | 5/23/2005 | 5/23/2005 | P | FAIL |
Forrest France
|
|
|
Pendent heads in hallway need to match response rating per NFPA 13 8.3.3.2. Upright heads above spray room are overspaced, need to meet 130 sq foot req. Perform hydrostatic test per. review notes.
|
INSP-Final Inspection | 5/3/2005 | 5/4/2005 | 5/4/2005 | A | CANC |
Forrest France
|
|
|
Cancel inspection per general contractor, not ready..
|
INSP-Final Inspection | 5/2/2005 | 5/3/2005 | 5/3/2005 | P | CANC |
Troy Cobbley
|
|
|
harry; Phone #: ###-#### Ran out of time to do inspection.
|
INSP-Sprinkler Rough-in | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | FAIL |
Forrest France
|
|
|
Fail inspection, fire sprinkler changes in spray booth and exterior compressor room not completed.
|
INSP-Final Inspection | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | FAIL |
Forrest France
|
|
|
Re-submitted approved plans and notes not available for review. Job supervisor seeks temp. occupancy approval.
|