Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR05-00169
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 917 S LUSK ST
Project Namealm - KEYNETICS
Customer Number 
ePlanReview 
Description
To provide a required manual fire alarm system. The required manual fire alarm system includes sprinkler monitoring, HVAC shutdown, elevator recall/shutdown and notification throughout. At this time, the core areas (defining walls) indicated on the drawings are "for future TI work", notification has been included in the restrooms, elevator lobby areas and what will appear to be the "future corridors". NO OCCUPANCY is allowed. Future TI work for the 2nd or 3rd floors will require the 1st floor main corridor to be completed and properly covered with visual notification appliances.

The associated building permit (BLD 04-02409) is to construct a new 27,958 sq.ft. three story, metal frame exterior walls, concrete floors, metal roof deck and a roof top structure for mechanical equipment. Each floor is approximately 9,172 sq.ft. with interior CMU walls around restrooms and stair enclosures, metal framed walls located at lobby and entry areas. NOTE: This building is fully fire sprinklered for story and area increase. All construction per the approved plans and attached comment list. Separate plans and permits must be obtained to finish each tenant area. Refer to BLD 04-02444 for the grading. MJP DRH 04-0118 CUP 04-0063 Note: This building is within the 100 year floodplain. Two elevation certificates required (one prior to issuance of permit and the other after first floor is installed). First elevation certificate received 11/18/04 by J. Wyllie, Public Works. Keynetics Office (shell & core) -

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/16/200512/19/200512/19/2005PPASS
DetailsForrest France
Items on correction notice have been completed, alarm tested satisfactory, permit finaled.
INSP-Final Inspection12/14/200512/15/200512/15/2005PFAIL
DetailsForrest France
Vent tube at duct detector 1st floor is incorrect, smoke detector at the electrical room 2nd floor is too close to the wall, 2nd and 3rd floor strobe in the common corridor is too low, pull station at the north roof is not functional, horn in the mech. penthouse is not operational, need to update map reflecting actual location of the floor control valves for the sprinkler system, not a complete inspection at this time, need to repair defficiencies and call for reinspect.