Permit Information
Permit NumberFIR05-00185
StatusFinaled
Name PEAK ALARM
Site Address 5010 -5350 W OVERLAND RD
Project Namealm - HILLCREST SHOPPING CNTR
Customer Number 
ePlanReview 
Description
FIR05-00185 is to upgrade the existing fire alarm system (a single FACP) in the shopping center. (A copy of the upgrade agreement is on sheet F0.0.) A required manual fire alarm system is required in the northwest corner of the center (Mike's Restaurant, Primerica, Calvary Chapel, Stage Coach Theatre and Heart and Home) due to the A occupancy load. The remainder of the shopping center will consist of sprinkler monitoring, HVAC shutdown and cooking hood monitoring. Albertson's has its' own FACP and will be allowed to do so due to the fire barriers that separate fire areas.

The associated building permit (BLD 05-00660) is to extend existing 1-hr fire barrier walls through the canopy at the Hillcrest Shopping Center. The fire barriers will define separate fire areas for alarm systems. The new 1-hr fire barrier walls installed in the canopy shall be continuous through concealed spaces within the canopy and shall extend at least 18" below the canopy ceiling. Existing fire barrier walls shall be extended and upgraded, if necessary, to create a complete separation where it is deficient. Openings shall be protected and penetrations fire stopped. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW** (HILLCREST SHOPPING CENTER - CODE UPGRADE) This building is required to be fire sprinklered because it is an unlimited area building.

FIR05-00186 is to provide monitoring of a cooking hood and two duct smoke detectors for HVAC shutdown to the existing required sprinkler monitoring system.

The associated building permit (BLD 04-02195) is to convert an existing 4,450 square foot tenant space to a restaurant (4,085 square foot main floor and 365 square foot mezzanine). This space was formerly used for retail sales. Work is to include interior nonbearing walls, two restrooms accessible to the disabled, a grease hood and duct, a hood and duct over a dishwasher, a stairway to serve the existing mezzanine, upgraded and extended 1-hr fire barrier walls, and interior finishes all per the approved drawings and the plan review report on file. Within the remodel area, the fire sprinkler heads shall be located or relocated to comply with NFPA 13-2002 as regulated by the Fire Department. **CJW** (MONGOLIAN BISTRO - HILLCREST SHOPPING CENTER) This building is fire sprinklered for unlimited area of the building.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro9/2/20059/6/20059/6/2005 PASS
Fire alarm permit finaled.
DOC - Permit Finaled  9/6/2005 DONE
Permit finaled.
INSP-Final Inspection8/31/20059/2/20059/2/2005 CANC
No time today for this re-inspection, spoke with Ray to schedule for next week.
INSP-Final Inspection8/31/20059/1/20059/1/2005 PART
Completed testing of all devices and re-tested defficient items. All issues are satisfactory except the outside bell at Fred Meyers and Mongolian Bistro failed to function properly.
INSP-Final Inspection8/30/20058/31/20058/31/2005 PART
Inspected devices at the dollar store riser, dry cleaners, golf store, knox box, and all relocated pull stations in the west portion of shopping center.
INSP-Final Inspection8/29/20058/30/20058/30/2005 CANC
No time available for this inspection today, ray to schedule for tomorrow at 9:00am per our agreement.
INSP-Final Inspection8/25/20058/26/20058/26/2005 PART
Finished testing central riser stack, tested east riser, tested tamper in pit, need to install and test outside electric bell at riser next to mongolian bistro, testing complete through FP1.4.
INSP-Final Inspection8/24/20058/25/20058/25/2005 CANC
Spoke with the contractor to reschedule this inspection for friday the 26th due to time constraints today.
INSP-Final Inspection8/22/20058/24/20058/24/2005 FAIL
Antifreeze tamper at the golf store failed to operate correctly, two wet system inspectors test connections lack a proper test orfice, additional tamper at west riser is not shown on plan, the riser next to Mongolian Bistro lacks an outside bell, all items tested today through sheet FP1.3, the liquor store on sheet FP1.4 tested okay. Need to provide copy of signal verification as requested.
INSP-Final Inspection8/22/20058/23/20058/23/2005 FAIL
One horn strobe device in the Stage Coach theater seating area failed to operate, an additional horn strobe is required in the lounge area at Mikes Restaurant due to a mirrored soffit obstruction, one storage room adjacent to the lounge is missing notification, several pull stations are mounted 1/2" too high, todays inspection completes all areas up to the first west fire separation wall.
INSP-Final Inspection8/19/20058/22/20058/22/2005 PART
Testing today included Fred Meyer, Honks and Heart and Home stores. The outside bell at Fred Meyers failed to operate, a manual pull station at the main exit from the Heart and Home store is mounted too high, all other items in these areas tested today are acceptable.
INSP-Alarm Testing8/18/20058/19/20058/19/2005 PART
All that was tested today and passed was the phone lines, battery draw, the smoke detector above the main facp and the interconnection between the fire alarm panel and the NAC panels. What did not pass today was the loss of a/c power was not detected on the stagecoach NAC panel and the NAC panels are not labeled to match the map and the plans. They need to show up on the panel as #1, #2 and #3. Also loss of batteries comes in labeled as a gate valve. These points between the NAC's and the main facp need to be retested to verify that the description/device matches the action. Per the alarm contractor the tamper switch in the pit is off line due to construction of a water line that damaged that part of the circuit.
INSP-Final Inspection8/17/20058/18/20058/18/2005 CANC
DetailsTroy Cobbley
ray; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
INSP-Final Inspection7/7/20057/7/20057/7/2005PFAIL
DetailsTroy Cobbley
Did not start inspection. Contractor stated that the three NAC panels are not sync'd as required. Hood in Mike's Restraunt was not finished. Existing sprinkler devices had not been pre-tested.