INSP-Final Inspection | 8/23/2005 | 8/23/2005 | 8/23/2005 | P | PASS |
Forrest France
|
|
|
Calculations for spacing have been verified. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/19/2005 | 8/19/2005 | 8/19/2005 | P | FAIL |
Troy Cobbley
|
|
|
Still need to verify that the sprinkler spacing in the conference room and the additional dry pendants are approved with resubmittals.
|
INSP-Final Inspection | 8/17/2005 | 8/17/2005 | 8/17/2005 | P | FAIL |
Troy Cobbley
|
|
|
Forward flush passed but need to certify the backflow preventor, provide verification of the spacing in the conference room and the additional dry pendants with bill as previously requested. Verify that the valve for the ball drip in the pit is open
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2005 | 7/7/2005 | 7/7/2005 | P | PASS |
Troy Cobbley
|
|
|
Wet system hydro test passed. Sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2005 | 6/30/2005 | 6/30/2005 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed on dry system
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2005 | 6/29/2005 | 6/29/2005 | P | PART |
Troy Cobbley
|
|
|
Started 24 hour air test with 50psi on guage.
|
INSP-Sprinkler Rough-in/Hydro | 6/16/2005 | 6/16/2005 | 6/16/2005 | P | PASS |
Troy Cobbley
|
|
|
200 lb hydro test on the dry pipe system passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PART |
Troy Cobbley
|
|
|
The remaining part of the dry system passed. Not all arm overs have been installed and will need inspected. Final head spacing to be checked when t-bar is installed.
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2005 | 6/3/2005 | 6/3/2005 | P | PART |
Troy Cobbley
|
|
|
See city approved plans for location where wet system can be covered as of 6/3/05.
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2005 | 6/1/2005 | 6/1/2005 | P | PART |
Troy Cobbley
|
|
|
The dry system rough-in is ok except for one head needs to be added in the south east room. Contractor needs to get with Bill Alexander to see if a resubmittal will be required for this head and the three other dry uprights added at each of the entrances.
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | PART |
Troy Cobbley
|
|
|
Sprinkler piping in the west drive thru canopy can be covered. As stated in the previous inspection entry, plans need to be resubmitted due to changes.
|
INSP-Supply line flush | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush and underground hydro test passed. I had contractor measure leakage. 5 1/2 quarts was allowed and it lost approx. 2 1/2 to 3 quarts
|
INSP-Sprinkler Rough-in | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | FAIL |
Troy Cobbley
|
|
|
I started rough-in inspection on the dry system at the request of the onsite sprinkler fitter but could not do the inspection due to pipe routing and sizing not matching approved plans. Upright heads are not spaced in accordance with NFPA 13 for obstruct
|