INSP-Final Inspection | 1/4/2006 | 1/5/2006 | 1/5/2006 | A | PASS |
Forrest France
|
|
|
The remaining portions of the alarm permitted work passed final inspection.
|
INSP-Final Inspection | 12/21/2005 | 12/22/2005 | 12/22/2005 | A | PASS |
Forrest France
|
|
|
Defficient issues have been corrected, inspection passed.
|
INSP-Final Inspection | 12/20/2005 | 12/21/2005 | 12/21/2005 | A | FAIL |
Forrest France
|
|
|
Strobe in the staff break room is blocked by a wall not shown on plans, coverage in this area is incomplete, relocate or add an additional device, all other items tested okay.
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2005 | 9/27/2005 | 9/27/2005 | P | PASS |
Forrest France
|
|
|
Items on correction notice have been completed, fire alarm passed inspection.
|
INSP-Final Inspection | 9/23/2005 | 9/26/2005 | 9/26/2005 | A | FAIL |
Forrest France
|
|
|
SD is overspaced in file room, SD in two adjacent rooms as marked on plans are too close to HVAC diffusers, one strobe in restroom with drop ceiling is mounted too high, all other items tested okay, provide latest resubmittals at next inspection.
|
INSP-Alarm Testing | 6/22/2005 | 6/23/2005 | 6/23/2005 | A | PART |
Forrest France
|
|
|
Fire alarm inspection satisfactory for exit corridor, women's lockers and restrooms, and southeast portion of area C.
|
INSP-Conference | 5/31/2005 | 6/1/2005 | 6/1/2005 | A | DONE |
Forrest France
|
|
|
Done. Walk through with Phil Doble and Dave Hannah area C. Discussed project phasing and inspection schedule.
|