INSP-Final Inspection | 12/22/2005 | 12/22/2005 | 12/22/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/22/2005 | 12/22/2005 | 12/22/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection, c/n items are complete.
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2005 | 11/17/2005 | 11/17/2005 | P | FAIL |
Forrest France
|
|
|
Hydrostatic test started but failed midway due to pipe breakage per phone call from the GC.
|
INSP-Sprinkler Rough-in/Hydro | 11/9/2005 | 11/10/2005 | 11/10/2005 | P | CANC |
Troy Cobbley
|
|
|
No time for inspection
|
INSP-Sprinkler Rough-in | 8/24/2005 | 8/24/2005 | 8/24/2005 | P | PART |
Forrest France
|
|
|
Underground fire supply line stub out to 8' of building is good for cover.
|
INSP-Sprinkler Rough-in | 8/17/2005 | 8/17/2005 | 8/17/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply line between the restaurant and the boarding house is acceptable to cover with the sleeve installed per Bill Alexander.
|
INSP-Sprinkler Rough-in | 8/16/2005 | 8/16/2005 | 8/16/2005 | P | FAIL |
Forrest France
|
|
|
Provide the correct set of approved drawings for this inspection, steel pipe is not allowed for underground fire service applications unless specifically listed.
|
INSP-Sprinkler Rough-in | 8/16/2005 | 8/17/2005 | | A | |
Forrest France
|
|
|
###-#### - bruce Note: after morning 9:00 ish
|