INSP-Final Inspection | 9/6/2005 | 9/7/2005 | 9/7/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/31/2005 | 9/1/2005 | 9/1/2005 | A | FAIL |
Forrest France
|
|
|
Incomplete coverage at front of store next to entryway, upright head is blocked by a soffit below.
|
INSP-Conference | 8/16/2005 | 8/16/2005 | 8/16/2005 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Jeff at treasuer valley fire and he will follow up on status of the fire sprinkler permit
|
INSP-Final Inspection | 5/31/2005 | 5/31/2005 | 5/31/2005 | P | PART |
Troy Cobbley
|
|
|
Piping still does not match plans. Per sam rogers a temp is ok until plans have been resubmitted
|
INSP-Final Inspection | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | CANC |
Troy Cobbley
|
|
|
Per Adam the plans have not been resubmitted yet as requested at the last inspection
|
INSP-Final Inspection | 5/20/2005 | 5/20/2005 | 5/20/2005 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit plans showing the correct floor plan, main location, piping size and deletion of head at front of store. Provide sprinkler coverage in the entry since entry soffit and overhead duct combined exceed 4'.
|
INSP-Sprinkler Rough-in/Hydro | 5/18/2005 | 5/19/2005 | 5/19/2005 | A | CANC |
Troy Cobbley
|
|
|
To be done when building is ready to final.
|