Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR05-00271
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2466 -2510 N BOGUS BASIN RD
Project NameSPR HIGHLANDS VILLAGE BLD 7
Customer Number 
ePlanReview 
Description
HIGHLANDS VILLAGE BLD #7 * 2466, 2464, 2508 & 2510 N. Bogus Basin Rd. To install approximately 58'-0" of 4" C-900 PVC on the north and around the west side south, and up with a 4" D.I. riser piece to approximately 6" above concrete floor grade and to install overhead fire sprinkler protection throughout a new 13,266-ft/2 three story, four unit apartment building. The first floor is 4,346-ft/2 of which 2,912-ft/2 is for the garages (protected to Ordinary Group design) and the remaining is common area, (Light Hazard design). The second floor is 4,440-ft/2 and the third floor is 4,440-ft/2. These residential floors will be protected with a 13R design. Each unit on the second and third floors are single story units. This building is fire sprinklered per NFPA 13R for story increase. The fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work. This permit is attached to building permit: BLD04-00942.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/29/20073/30/20073/30/2007APASS
DetailsForrest France
Corrections verified for completion, fire sprinkler passed inspection, permit finaled.
INSP-Final Inspection3/26/20073/27/20073/27/2007AFAIL
DetailsForrest France
Missing escutcheons at several locations, need to complete forward flow testing with a functional pitot guage.
INSP-Sprinkler Rough-in/Hydro3/24/20073/26/20073/26/2007PPART
DetailsForrest France
OH hydrostatic test completed satisfactory, noted leakage at the drain connection piping to be repaired prior to next inspection.
INSP-Sprinkler Rough-in/Hydro12/20/200612/22/200612/22/2006APART
DetailsForrest France
Approval for overhead fire sprinkler cover on the first and second floors of building #7 only. Third floor will require an inspeciton for cold cavity protection prior to cover.
INSP-Sprinkler Rough-in12/19/200612/20/200612/21/2006APART
DetailsTroy Cobbley
Sprinkler rough-in is mostly passed. Four overspaced heads were relocated while I performed the inspection. The first floor sprinkler piping can be covered except the garage as marked on the plans where the 1 1/2" main has actually be installed with with 2". Additional heads have been installed in closets that weren't shown in the first floor lobby. The second floor is ok to cover. The third floor can not be covered until a tenting inspection has been performed. Also on the third floor additional heads have been added in the bedrooms. One of these bedrooms is a remote area. Plans need to be resubmitted showing all of the addtional heads and piping reroutes. Also revised hydraulic calculations need to be resubmitted to verify the pipe size change on the first floor and the additional head that may need to be included in the remote area on the third floor.
INSP-Sprinkler Rough-in12/18/200612/19/200612/19/2006PCANC
DetailsForrest France
No time available to complete this inspection today.
INSP-Supply line flush12/6/200612/6/200612/6/2006PPART
DetailsForrest France
UG supply line flush completed.
INSP-Supply line flush11/29/200611/30/200611/30/2006ACANC
DetailsTroy Cobbley
bryan was unable to do the flush today
INSP-Sprinkler Rough-in/Hydro11/29/200611/30/200611/30/2006APASS
DetailsTroy Cobbley
Underground hydro test passed.
INSP-Sprinkler Rough-in10/31/200510/31/200510/31/2005PPASS
DetailsTroy Cobbley
Underground supply piping is ok to cover.