INSP-Final Inspection | 3/29/2007 | 3/30/2007 | 3/30/2007 | A | PASS |
Forrest France
|
|
|
Corrections verified for completion, fire sprinkler passed inspection, permit finaled.
|
INSP-Final Inspection | 3/26/2007 | 3/27/2007 | 3/27/2007 | A | FAIL |
Forrest France
|
|
|
Missing escutcheons at several locations, need to complete forward flow testing with a functional pitot guage.
|
INSP-Sprinkler Rough-in/Hydro | 3/24/2007 | 3/26/2007 | 3/26/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test completed satisfactory, noted leakage at the drain connection piping to be repaired prior to next inspection.
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2006 | 12/22/2006 | 12/22/2006 | A | PART |
Forrest France
|
|
|
Approval for overhead fire sprinkler cover on the first and second floors of building #7 only. Third floor will require an inspeciton for cold cavity protection prior to cover.
|
INSP-Sprinkler Rough-in | 12/19/2006 | 12/20/2006 | 12/21/2006 | A | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in is mostly passed. Four overspaced heads were relocated while I performed the inspection. The first floor sprinkler piping can be covered except the garage as marked on the plans where the 1 1/2" main has actually be installed with with 2". Additional heads have been installed in closets that weren't shown in the first floor lobby. The second floor is ok to cover. The third floor can not be covered until a tenting inspection has been performed. Also on the third floor additional heads have been added in the bedrooms. One of these bedrooms is a remote area. Plans need to be resubmitted showing all of the addtional heads and piping reroutes. Also revised hydraulic calculations need to be resubmitted to verify the pipe size change on the first floor and the additional head that may need to be included in the remote area on the third floor.
|
INSP-Sprinkler Rough-in | 12/18/2006 | 12/19/2006 | 12/19/2006 | P | CANC |
Forrest France
|
|
|
No time available to complete this inspection today.
|
INSP-Supply line flush | 12/6/2006 | 12/6/2006 | 12/6/2006 | P | PART |
Forrest France
|
|
|
UG supply line flush completed.
|
INSP-Supply line flush | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | CANC |
Troy Cobbley
|
|
|
bryan was unable to do the flush today
|
INSP-Sprinkler Rough-in/Hydro | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover.
|