Permit Information
Permit NumberFIR05-00282
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1151 W MILLER ST
Project NameSPR OH SMARC LLC, IDX PATHOLOG
Customer Number 
ePlanReview 
Description
(SMARC LLC, IDX PATHOLOGY) To install a complete overhead fire sprinkler system in an existing 11,803-ft/2 building, consisting of 8,532-ft/2 warehouse & 3,271-ft/2 of office; to be used as a medical office & laboratory. This building is being fully renovated by selective demolition and construction of new interior walls for offices, reception, customer service, conference, support/laboratory work areas, two restrooms; new entry vestibule. U.G. Fire Service Supply issued under FIR05-00206. The building will be fully sprinklered. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-000282.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/25/20057/25/20057/25/2005PPASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection7/20/20057/20/20057/20/2005PCANC
DetailsForrest France
Cancel per Troy with Treasure Valley Sprinkler, project not ready for final inspection.
INSP-Sprinkler Rough-in/Hydro6/20/20056/20/20056/20/2005APART
DetailsForrest France
Overhead hydrostatic test passed inspection.
INSP-Sprinkler Rough-in6/20/20056/20/20056/20/2005PFAIL
DetailsForrest France
Verify correct size orfice on inspectors test, verify sammy screw size is listed for 2 1/2" pipe attatched vertically, overspaced longitudinal EQ brace, SSU above break room is too far below deck, provide as-builts for added head at entry and in accounting room, verify uprights after paint paper is removed, check L09 for blockage per. NFPA 8.6.5.1.2 at exposed beam- possibly not meeting density req. from L08.
INSP-Sprinkler Rough-in/Hydro6/16/20056/16/20056/16/2005PCANC
DetailsForrest France
Wrong permit number called in. This inspection was for UG hydro and flush under permit fir05-00206 at the same address under the same building permit.