Permit Information
Permit NumberFIR05-00312
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 11580 W FAIRVIEW AVE
Project NameSPR COLTRIN BUILDING
Customer Number 
ePlanReview 
Description
COLTRIN BUILDING (SHELL) -To install a new overhead wet and dry pipe fire sprinkler system in a 18,490-ft/2, two story, type V-B, fully fire sprinklered office/retail shell building. First floor 14,000-ft/2, 2nd floor 4,490-ft/2. No occupancy is authorized by this permit. Fire sprinklers are used for area and story increase. The underground fire service supply main was installed under FIR05-00222. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD04-02020.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/14/20062/15/20062/15/2006APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection2/7/20062/7/20062/7/2006PPART
DetailsTroy Cobbley
A temporary occupancy was given with Dave Hannemans permission until issues with the shell building have been corrected.
INSP-Final Inspection2/2/20062/3/20062/3/2006PFAIL
DetailsTroy Cobbley
Provide approved hangers for th 4" main. Provide correct attachment for the eq bracing. Provide forward flush. Provide review comments. Provide correct air compressor and air maintenance device.
INSP-Sprinkler Rough-in1/25/20061/26/20061/26/2006PPASS
DetailsTroy Cobbley
Sprinkler piping in the second floor attic and the east tenant improvement space are ok for cover
INSP-Sprinkler Rough-in1/17/20061/19/20061/19/2006APART
DetailsTroy Cobbley
The south wing piping in the attic area is ok to cover with insulation
INSP-Supply line flush1/4/20061/5/20061/5/2006APASS
DetailsTroy Cobbley
Underground flush passed
INSP-Supply line flush1/4/20061/4/20061/4/2006PFAIL
DetailsTroy Cobbley
united water did not show up
INSP-Sprinkler Rough-in12/9/200512/12/200512/12/2005AFAIL
DetailsTroy Cobbley
No inspection is supposed to be called in but I did it anyway. Alot of changes have taken place with the piping. Per fitter these changes are reflected on another resubmittal that is in for review. This includes heads repiped and added in the second floor dry remote area, branchline added on the lower level dry system and main reroutes. Dry system heads dont meet 8.6.5.2.1.6 for spacing.
INSP-Sprinkler Rough-in11/22/200511/23/200511/22/2005PCANC
DetailsTroy Cobbley
No time for inspection
INSP-Sprinkler Rough-in11/21/200511/22/200511/22/2005ACANC
DetailsTroy Cobbley
No time for inspection
FIR-Aging Inspection9/8/20059/8/20059/13/2005 NR
DetailsTroy Cobbley
Work is in progess. Job only has a partial approval. Resubmittals required.