VISTA VILLAGE SHOPPING CENTER-PHASED (BUILDING "E" UNDERGROUND) * Phase 1 is to stub out 5'-0" of 6" C-900 CPVC underground fire service supply and install a 6" underground riser located in the North East corner of a new, single story 6,135-ft/2 retail multi-tenant shell building with a 800-ft/2 covered entry facade. Phase 2 is to continue north 20'-0" then 90° west approximately 190'-0" with two 45º offsets and connect to the (United Water) tap at the property line at Vista. This building will be fully fire sprinklered. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002, AWWA, the IFC-2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD05-00315.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/19/20061/19/20061/19/2006PPASS
DetailsForrest France
UG permit finaled.
INSP-Final Inspection1/19/20061/19/20061/19/2006PPASS
DetailsForrest France
UG fire supply line permit passed final inspection.
INSP-Supply line flush9/8/20059/8/20059/8/2005PPART
DetailsForrest France
Underground fire supply line flush is satisfactory.
INSP-Sprinkler Rough-in/Hydro8/8/20058/8/20058/8/2005PPART
DetailsForrest France
UG fire supply hydrostatic test passed.
INSP-Sprinkler Rough-in8/5/20058/5/20058/5/2005PPART
DetailsForrest France
Underground fire supply is acceptable to cover.
INSP-Supply line flush8/3/20058/4/20058/4/2005PFAIL
DetailsForrest France
Inspection was for an UG hydrostatic test and phase two UG cover inspection. Two 45 degree joints, the testing blank and a thrust block at the 90 are buried, preventing inspection The hydrostatic test was not ready.
INSP-Sprinkler Rough-in6/10/20056/10/20056/10/2005PPART
DetailsForrest France
Fire supply UG stub out and riser piece OK to cover. Verify seismic clearance and that no C900 is exposed above floor slab at a later date.