INSP-Final Inspection | 11/21/2005 | 11/22/2005 | 11/22/2005 | A | PASS |
Forrest France
|
|
|
Correction notice items have been completed, submit as-builts reflecting pipe routing changes as required.
|
INSP-Final Inspection | 11/16/2005 | 11/17/2005 | 11/17/2005 | A | PART |
Forrest France
|
|
|
Correction notice items have been completed, final pending forward flow, alarms, ceiling tile and canopies, and fill the annular space at UG penetration.
|
INSP-Final Inspection | 11/15/2005 | 11/15/2005 | 11/15/2005 | P | FAIL |
Forrest France
|
|
|
Fail inspection due to numerous issues still not corrected, a 13 item c/n was left with Nick of Guho const., not all items inspected at this time-third floor not inspected as well.
|
INSP-Final Inspection | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | CANC |
Forrest France
|
|
|
Out of time, no inspection performed.
|
INSP-Final Inspection | 11/9/2005 | 11/10/2005 | 11/10/2005 | P | CANC |
Troy Cobbley
|
|
|
no time for inspection
|
INSP-Supply line flush | 11/2/2005 | 11/3/2005 | 11/3/2005 | P | FAIL |
Forrest France
|
|
|
Provide resubmittals as required indicating information as requested on plan review notes and all field changes from original plans, overhead inspection failed due to numerous issues including spacing, head temps., bracing, seismic clearance, obstructions to discharge, riser not complete, etc., the UG was flush was performed and is acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 10/31/2005 | 11/1/2005 | 11/1/2005 | P | PART |
Forrest France
|
|
|
Overhead and underground hydrostatic tests are satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2005 | 10/28/2005 | 10/28/2005 | A | CANC |
Forrest France
|
|
|
No time available for this inspection today due to BODO projects.
|
INSP-Sprinkler Rough-in | 9/8/2005 | 9/8/2005 | 9/8/2005 | P | PART |
Forrest France
|
|
|
The upright heads above hard lid areas on 2nd floor hall in front of the restrooms are okay to cover.
|