INSP-Final Inspection | 3/28/2006 | 3/29/2006 | 3/29/2006 | A | PASS |
Forrest France
|
|
|
Items on previous correction notices have been completed, fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/17/2006 | 3/20/2006 | 3/20/2006 | A | FAIL |
Forrest France
|
|
|
Some items on previous correction notice dated 11/10/05 have not been completed including the missing escutcheon at the womens restroom lobby area, missing coverage at the roof hatch. Two heads in the east projection room are spaced incorrectly for min. spacing, no access to storage room next to managers office for OH spacing verification. Plans have been resubmitted for OH spacing at the projection rooms, however an alternate agreement for "no storage allowed" has been accepted in lieu of sprinkler modifications.
|
INSP-Final Inspection | 11/10/2005 | 11/10/2005 | 11/10/2005 | P | CANC |
Forrest France
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Barbara Moore- cambry cancel 9:05 pm
|
INSP-Final Inspection | 11/10/2005 | 11/10/2005 | 11/10/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hanniman's permission. Items needing correction include the east and west projector rooms need to be designed/spaced for OH2, the roof access hatch requires protection, the storage room next to the managers office needs to be OH2, pendant over the escalator in the east entry lobby is overspaced 196 max, submit the correcte plans including the concession area, replace the missing canopy in the lobby/womens restroom and patch hole and remove all storage from the projection room. All of the items need to be corrected within 30 days.
|
INSP-Final Inspection | 11/9/2005 | 11/9/2005 | 11/9/2005 | P | FAIL |
Forrest France
|
|
|
An additional 11 item correcton notice was given to the subcontractor, inspection stopped at this point due to the excessive number of defficiencies. Mezzanine not inspected for final yet, contractor to walk project again and call for re-inspection when project is code compliant. Re-inspection fees apply.
|
INSP-Final Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 | P | FAIL |
Forrest France
|
|
|
Missing two escutcheons at box office area, two heads at the concession bar are spaced incorrectly, one head in the men's restroom is blocked by a column, head appears overspaced at atrium above east escalators, the inspection was concluded at this time-contractor to walk through project and reschedule inspection when complete.
|
INSP-Sprinkler Rough-in/Hydro | 10/28/2005 | 11/1/2005 | 11/1/2005 | P | PART |
Forrest France
|
|
|
Provide resubmittals, clock tower has unprotected combustible construction, tenant demising walls obstruct coverage in some areas, theatre needs final walk -through.
|
INSP-Final Inspection | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | FAIL |
Forrest France
|
|
|
Approval pending items remaining on correction notice including forward flow test, roof standpipe flow test, heads under overhead door at riser, resubmittals for box office changes, tenant demising wall coverage obstructions, lacking coverage in clock tower for combustibles, escutcheons at locations in theatre spaces.
|
INSP-Sprinkler Rough-in | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | FAIL |
Forrest France
|
|
|
See correction notices for listing of defficient items.
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2005 | 10/27/2005 | 10/27/2005 | A | FAIL |
Forrest France
|
|
|
Sheet FP2 only for overhead shell rough-in inspected and an 18 item correction notice issued.
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2005 | 10/26/2005 | 10/26/2005 | P | DEFR |
Forrest France
|
|
|
Inspection to be completed tomorrow AM.
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2005 | 10/25/2005 | 10/25/2005 | P | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test of theatres and mezzanine off floor control valve south stair lost approx. 2 psi, contractor to have checked tomorrow for re-inspect. Contractor is not ready for overhead rough-in inspection for the shell at this time.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2005 | 10/20/2005 | 10/20/2005 | A | PART |
Forrest France
|
|
|
Witnessed testing and start up of the fire pump, tested at 150%, 100%, rated flow and shutoff, tested jockey pump, need to run drain from pump casing, need to install sensing lines per NFPA 20.
|
INSP-Sprinkler Rough-in | 10/18/2005 | 10/20/2005 | 10/20/2005 | A | NR |
Forrest France
|
|
|
Per Matt the shell rough-in is not ready for inspection at this time.
|
INSP-Sprinkler Rough-in/Hydro | 10/18/2005 | 10/19/2005 | 10/19/2005 | A | FAIL |
Forrest France
|
|
|
The box office overhead hydro lost pressure to 197 psi., the UG supply hydro lost 5 psi., the standpipe, office depot shell area, and ann taylor area not tested at this time.
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2005 | 10/13/2005 | 10/13/2005 | A | CANC |
Forrest France
|
|
|
contact: matt - UG hydro test and hydro test for box office.; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 10/3/2005 | 10/3/2005 | 10/3/2005 | P | FAIL |
Forrest France
|
|
|
Inspection was for cover at hard lids in the main box office lobby area first floor on sheet FP2. Fail inspection, provide resubmittals for several changes in pipe routing from the approved plans, two heads are 5' apart, one retaining strap is not fastened to the beam, not all heads are cut in.
|
INSP-Sprinkler Rough-in | 8/30/2005 | 8/31/2005 | 8/31/2005 | A | FAIL |
Forrest France
|
|
|
Two heads in 2nd floor restroom hard lid are spaced 5' apart, missing retaining strap on hanger in hallway, incorrect head spacing at soffit as marked on approved plans, inspection was for sheet FP 5 second floor.
|
INSP-Sprinkler Rough-in | 8/18/2005 | 8/18/2005 | 8/18/2005 | P | CANC |
Forrest France
|
|
|
matt; Phone #: ###-#### Cancel inspection per Matt, he will reschedule for tomorrow.
|
INSP-Sprinkler Rough-in | 8/8/2005 | 8/9/2005 | 8/9/2005 | A | FAIL |
Forrest France
|
|
|
Missing 4-way EQ brace on atrium main, heads in east soffit are overspaced, one line is installed as 1" pipe--the plan shows 11/4 pipe, missing head in lower west soffit hard lid, need to verify there are no obstructions to coverage caused at the juncture of soffits and grid ceiling when the grid is installed.
|
INSP-Sprinkler Rough-in | 7/25/2005 | 7/26/2005 | 7/26/2005 | P | PART |
Forrest France
|
|
|
2nd floor projection room and mezzanine, theatres #8 and #9 are good for cover. Final head location will be examined after ceiling grid is installed. Approved rough-in areas are initialed on stamped plan set.
|
INSP-Sprinkler Rough-in | 7/21/2005 | 7/22/2005 | 7/22/2005 | P | CANC |
Forrest France
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 7/13/2005 | 7/14/2005 | 7/14/2005 | P | CANC |
Forrest France
|
|
|
Cancel inspection per contractor, not ready.
|
INSP-Sprinkler Rough-in | 7/12/2005 | 7/13/2005 | 7/13/2005 | P | CANC |
Forrest France
|
|
|
CONTACT MATT, R-IN. AFTER 3PM; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 7/12/2005 | 7/13/2005 | 7/12/2005 | P | CANC |
Forrest France
|
|
|
CONTACT MATT. R-IN.; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2005 | 7/8/2005 | 7/8/2005 | P | PART |
Forrest France
|
|
|
Rough-in at theatres 1,2,3,4,5,6,7 are good for cover, improper branch line hanger in theatre 1 repaired while on site. EQ 4 way bracing in theatre 2 and 6 to be amended so lateral and longitudinal connections at main are closer together. Proper head spacing to be verified when heads are installed in tile at final locations.
|