Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR05-00378
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 391 S 8TH ST
Project NameBODO BLDG #4 SPR
Customer Number 
ePlanReview 
Description
(P. F. CHANG'S CHINA BISTRO - BOBO BLDG 4) To relocate and add fire sprinkler protection in a new 7,500-ft/2 restaurant tenant space (3,315-ft/2 interior dining, 1,015-ft/2 covered exterior dining, 2,720-ft/2 kitchen, 450-ft/2 for the restrooms) within a (new shell) 2 story building. Fire sprinkler work is related to 2 restrooms, new interior nonbearing walls and suspended ceilings. The fire sprinkler system shall comply with 2002 NFPA 13 as regulated by the Fire Department. This building is fire sprinklered for building area increase and for fire area. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD05-00626.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/26/200510/27/200510/27/2005APASS
DetailsForrest France
Fire sprinkler passed inspection.
INSP-Final Inspection10/26/200510/26/200510/26/2005AFAIL
DetailsForrest France
Review notes were not available on site for inspection, escutcheons are missing in three locations
INSP-Sprinkler Rough-in/Hydro10/13/200510/13/200510/13/2005PPART
DetailsForrest France
Hydrostatic test of antifreeze system passed inspection.
INSP-Sprinkler Rough-in/Hydro10/10/200510/11/200510/11/2005PCANC
DetailsTroy Cobbley
Contact: Brian - Hydro Test; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley
INSP-Sprinkler Rough-in10/10/200510/11/200510/11/2005APART
DetailsTroy Cobbley
Provide 200 degree pendant in the utility room, finish installing ceiling and canopies, provide longitudinal bracing on the antifreeze main under canopy. Per Bill the 130 sq. ft. max spacing is a type error. 225 sq. ft. is allowed in the light hazard areas.
INSP-Sprinkler Rough-in9/22/20059/22/20059/22/2005PPART
DetailsForrest France
Overhead rough-in is okay for cover in the grid ceiling areas, will verify proper spacing and head temp. ratings at heat sources in the kitchen after all drops have been cut in. One branch line is directly over an electrical panel, this will need to be relocated per electrical code.
INSP-Sprinkler Rough-in8/19/20058/19/20058/19/2005APART
DetailsForrest France
Rough-in areas above hard lids are okay to cover, need to cut head in southwest soffit as discussed, GC to provide drop ceiling in storage room, antifreeze system is not complete or inspected at this time.
INSP-Sprinkler Rough-in/Hydro8/18/20058/19/2005 A 
DetailsUnknown
Contact: Jim - Cover Inspection; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro8/10/20058/12/2005 A 
DetailsUnknown
Contact: Brian Calkins - Rough In; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley