Permit Information
Permit NumberFIR05-00385
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 917 S LUSK ST
Project NameSPR KENETICS OH & PHASE 2 UG
Customer Number 
ePlanReview 
Description
KEYNETICS OFFICE (SHELL & CORE) - To install underground and overhead, Ordinary Group 1 and Light Hazard wet system with an extended supervised, electric pneumatic release, double interlock preaction system for a small area on the second floor, in a new 27,958-ft/2, three story, metal frame, exterior walled, concrete floored, metal roof decked, with a roof top mechanical equipment structure. Each floor is approximately 9,172-ft/2 with interior CMU walls around restrooms and stair enclosures. This building is fully fire sprinklered for story and area increase. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD04-02409.
*November 7, 2005 - Modification to a design submitted for demo existing wet pipe protection in the electrical room directly beneath the 2nd floor computer room.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/15/200512/15/200512/15/2005PPASS
DetailsForrest France
c/n items are complete, fire sprinkler permit finaled.
INSP-Sprinkler Rough-in/Hydro12/13/200512/14/200512/14/2005PDONE
DetailsForrest France
This duplicate inspection already called in has been completed, see c/n items listed.
INSP-Sprinkler Rough-in/Hydro12/13/200512/14/200512/14/2005APART
DetailsForrest France
Retest of the preaction system hydrostatic two hour test passed.
INSP-Sprinkler Rough-in12/13/200512/14/200512/14/2005APART
DetailsForrest France
Overhead is acceptable pending installation of missing escutcheons, ceiling tile, remove tape and paper at uprights where covered for painting, need heads in head box and wrench, perform forward flow, alarms, sign at bell.
INSP-Sprinkler Rough-in/Hydro12/13/200512/13/200512/13/2005PFAIL
DetailsTroy Cobbley
Pre-action hydro test failed.
INSP-Sprinkler Rough-in/Hydro12/12/200512/13/200512/13/2005APART
DetailsForrest France
Overhead hydrostatic test of the wet system passed inspection.
INSP-Sprinkler Rough-in/Hydro12/12/200512/13/200512/13/2005APART
DetailsForrest France
The 24 hr. air test for the preaction system passed.
INSP-Sprinkler Rough-in12/12/200512/12/200512/12/2005PPART
DetailsForrest France
First floor overhead rough-in is okay for cover at the grid ceiling areas only, began 24 hour air test at 9:30 am at 42psi.
INSP-Sprinkler Rough-in/Hydro12/1/200512/2/200512/2/2005APART
DetailsForrest France
2nd and 3rd floor only is okay for cover regarding rough-in, some sw and ssu heads are missing, various pendant heads are overspaced, sw heads are painted in some locations.
INSP-Sprinkler Rough-in11/30/200512/1/200512/1/2005PCANC
DetailsForrest France
Inspection to be rescheduled per agreement with Mike at ###-#### for 12/2 am.
INSP-Sprinkler Rough-in11/3/200511/3/200511/3/2005PPART
DetailsForrest France
The 3rd floor center common area hard lid area is acceptable for cover, also discussed coverage requirements for small room at perimeter and 2nd floor hard lid areas.
INSP-Sprinkler Rough-in10/7/200510/7/200510/7/2005PFAIL
DetailsForrest France
Upright heads at first floor landings in both stairways are overspaced, upright head is missing above restroom 1st floor, hanger is missing on an armover above restroom 3rd floor, provide resubmittals reflecting added uprights and pipe layout changes at restrooms 1st, 2nd, and 3rd floors.
INSP-Conference10/4/200510/4/200510/4/2005PDONE
DetailsForrest France
On site discussion regarding sprinkler coverage requirements at stair landings and cloud ceiling areas.
INSP-Sprinkler Rough-in/Hydro8/8/20058/9/20058/9/2005APART
DetailsForrest France
UG fire supply line hydrostatic test for phase one and two of underground work passed inspection.
INSP-Supply line flush8/8/20058/9/20058/9/2005APART
DetailsForrest France
Phase two UG fire supply line flush is satisfactory.
INSP-Supply line flush8/8/20058/8/20058/8/2005PCANC
DetailsForrest France
Cancel inspection per Sam, not ready, will reschedule for tomorrow.
INSP-Sprinkler Rough-in/Hydro8/8/20058/8/20058/8/2005PCANC
DetailsForrest France
Cancel inspection per Sam with Treasure Valley Sprinkler.