INSP-Final Inspection | 12/15/2005 | 12/15/2005 | 12/15/2005 | P | PASS |
Forrest France
|
|
|
c/n items are complete, fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/13/2005 | 12/14/2005 | 12/14/2005 | P | DONE |
Forrest France
|
|
|
This duplicate inspection already called in has been completed, see c/n items listed.
|
INSP-Sprinkler Rough-in/Hydro | 12/13/2005 | 12/14/2005 | 12/14/2005 | A | PART |
Forrest France
|
|
|
Retest of the preaction system hydrostatic two hour test passed.
|
INSP-Sprinkler Rough-in | 12/13/2005 | 12/14/2005 | 12/14/2005 | A | PART |
Forrest France
|
|
|
Overhead is acceptable pending installation of missing escutcheons, ceiling tile, remove tape and paper at uprights where covered for painting, need heads in head box and wrench, perform forward flow, alarms, sign at bell.
|
INSP-Sprinkler Rough-in/Hydro | 12/13/2005 | 12/13/2005 | 12/13/2005 | P | FAIL |
Troy Cobbley
|
|
|
Pre-action hydro test failed.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the wet system passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PART |
Forrest France
|
|
|
The 24 hr. air test for the preaction system passed.
|
INSP-Sprinkler Rough-in | 12/12/2005 | 12/12/2005 | 12/12/2005 | P | PART |
Forrest France
|
|
|
First floor overhead rough-in is okay for cover at the grid ceiling areas only, began 24 hour air test at 9:30 am at 42psi.
|
INSP-Sprinkler Rough-in/Hydro | 12/1/2005 | 12/2/2005 | 12/2/2005 | A | PART |
Forrest France
|
|
|
2nd and 3rd floor only is okay for cover regarding rough-in, some sw and ssu heads are missing, various pendant heads are overspaced, sw heads are painted in some locations.
|
INSP-Sprinkler Rough-in | 11/30/2005 | 12/1/2005 | 12/1/2005 | P | CANC |
Forrest France
|
|
|
Inspection to be rescheduled per agreement with Mike at ###-#### for 12/2 am.
|
INSP-Sprinkler Rough-in | 11/3/2005 | 11/3/2005 | 11/3/2005 | P | PART |
Forrest France
|
|
|
The 3rd floor center common area hard lid area is acceptable for cover, also discussed coverage requirements for small room at perimeter and 2nd floor hard lid areas.
|
INSP-Sprinkler Rough-in | 10/7/2005 | 10/7/2005 | 10/7/2005 | P | FAIL |
Forrest France
|
|
|
Upright heads at first floor landings in both stairways are overspaced, upright head is missing above restroom 1st floor, hanger is missing on an armover above restroom 3rd floor, provide resubmittals reflecting added uprights and pipe layout changes at restrooms 1st, 2nd, and 3rd floors.
|
INSP-Conference | 10/4/2005 | 10/4/2005 | 10/4/2005 | P | DONE |
Forrest France
|
|
|
On site discussion regarding sprinkler coverage requirements at stair landings and cloud ceiling areas.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2005 | 8/9/2005 | 8/9/2005 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test for phase one and two of underground work passed inspection.
|
INSP-Supply line flush | 8/8/2005 | 8/9/2005 | 8/9/2005 | A | PART |
Forrest France
|
|
|
Phase two UG fire supply line flush is satisfactory.
|
INSP-Supply line flush | 8/8/2005 | 8/8/2005 | 8/8/2005 | P | CANC |
Forrest France
|
|
|
Cancel inspection per Sam, not ready, will reschedule for tomorrow.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2005 | 8/8/2005 | 8/8/2005 | P | CANC |
Forrest France
|
|
|
Cancel inspection per Sam with Treasure Valley Sprinkler.
|