Permit Information
Permit NumberFIR05-00396
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 12550 W EXPLORER DR
Project NameSPR ALPINE BUILDING
Customer Number 
ePlanReview 
Description
ALPINE BUILDING (SHELL & CORE) - To install a complete overhead, standard spray, quick response sprinklers, for light hazard occupancy use, fire sprinkler system in a new 22,315-ft/2, two story, (1st floor 11,525-ft/2, 2nd floor 10,790-ft/2), concrete tilt-up office shell and core building. Fire sprinkler include finish work related to core area restrooms and janitor's closets on the first and second floors, entry and hallways, mechanical room and elevator machine room on the first floor, elevator and stairways. Separate tenant improvement permits will be required to finish this building for occupancy. The 2003 International Building Code, Section 1019, Exception #9 is being used as an alternate to the 2000 International Building Code, Section 1005.3.2 to allow two open stairways in a fully sprinklered building. The underground fire service supply was permitted by the same contractor under FIR05-00248. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-002346.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/29/200512/30/200512/30/2005PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection12/30/200512/30/200512/30/2005PPASS
DetailsTroy Cobbley
permit finaled
INSP-Alarm Testing12/28/200512/29/200512/29/2005PFAIL
DetailsTroy Cobbley
Plug sprinkler heads mounted horizontally in the T.I. space. Reinstall the ball drip at the FDC. Certify the backflow preventor. Relocate the bell to the FDC. Provide above ground hydro test papers.
INSP-Alarm Testing12/27/200512/28/200512/29/2005APASS
DetailsTroy Cobbley
The interconnection of the fire sprinkler devices and the fire alarm panel passed. I went over outstanding issues on the fire sprinkler system with Mike
INSP-Sprinkler Rough-in12/16/200512/19/200512/19/2005PDEFR
DetailsForrest France
Wrong permit number called in, this inspection was for the related TI work on the second floor rough-in for cover.
INSP-Sprinkler Rough-in/Hydro12/5/200512/7/200512/7/2005PPART
DetailsTroy Cobbley
Sprinkler rough-in passed for the most part. Heads are overspaced at the top of stairs 209 and in the restrooms. Maximum head spacing 120sq. ft. Riser piping not inspected with this overhead inspection.
INSP-Sprinkler Rough-in10/4/200510/5/200510/5/2005AFAIL
DetailsTroy Cobbley
Resubmittals required per the review comments. No inspection performed.