INSP-Final Inspection | 1/17/2006 | 1/17/2006 | 1/18/2006 | P | PASS |
Forrest France
|
|
|
c/n items are complete, plan items requiring resubmittal have been addressed with the TI submittals. Inspection passed.
|
INSP-Final Inspection | 1/9/2006 | 1/10/2006 | 1/10/2006 | P | FAIL |
Forrest France
|
|
|
Need to test alarms when complete, provide calc. sticker, pressure relief valve, main drain sign, perform forward flow, backflow certification, "911 sign" at bell, complete items on c/n. Overhead hydro test passed inspection at this time.
|
INSP-Sprinkler Rough-in/Hydro | 9/14/2005 | 9/15/2005 | 9/15/2005 | A | FAIL |
Forrest France
|
|
|
Bushings are not allowed in this application at the fittings on the north side grid main see NFPA 13 6.4.6.1, provide seismic clearance for the 2" and 3" mains where they pass through the masonry wall, upright heads at the south attic are over 15' apart, inspectors test orfice is not correctly sized, provide approved plans at next inspection, provide relief valve for gridded system at riser.
|