Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR05-00403
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2468- 2474 N BOGUS BASIN RD
Project NameSPR HIGHLANDS VILLAGE BLD 11
Customer Number 
ePlanReview 
Description
HIGHLANDS VILLAGE BLD #10, HARRISON FLOOR PLAN TYPE * 2468, 2470, 2472 & 2474 N. Bogus Basin Rd. To install overhead fire sprinkler protection throughout a new 10,716-ft/2, three story, four unit apartment building. The first floor is 3,806-ft/2 which 2,000-ft/2 is for the garages (protected to Ordinary Group design), the second floor is 3,946-ft/2 and the third floor is 2,964-ft/2 (Light Hazard design). Three units are three bedroom and three and one half baths, one unit is four bedroom and three and one half baths. This building is fire sprinklered per NFPA 13-R. The fire sprinkler system work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work. The underground fire service supply was installed under FIR04-00269. This permit is attached to building permit: BLD04-00946.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/7/20073/7/20073/7/2007PPASS
DetailsForrest France
Fire sprinkler passed final inspection, permit finaled.
INSP-Final Inspection2/22/20072/23/20072/23/2007APART
DetailsForrest France
Fire sprinkler permit work is ready for final pending satisfactory test of the riser supervisory and alarm devices per project related FA permit.
INSP-Sprinkler Rough-in10/10/200610/10/200610/10/2006PPASS
DetailsTroy Cobbley
third floor sprinkler piping can be covered
INSP-Conference10/3/200610/4/200610/4/2006AFAIL
DetailsTroy Cobbley
Insulation was not done yet.
INSP-Sprinkler Rough-in/Hydro9/11/20069/12/20069/12/2006PPART
DetailsForrest France
OH hydrostatic test passed inspection.
INSP-Sprinkler Rough-in9/8/20069/11/20069/11/2006APART
DetailsForrest France
OH rough-in is good for cover on the first and second floors only, third floor will require a tenting inspection prior to cover.
INSP-Sprinkler Rough-in9/7/20069/8/20069/8/2006PFAIL
DetailsTroy Cobbley
The piping sizing in the end garage where the remote area is does not match plan. Plan shows 1" piping but 2" is installed. Also the 3rd floor remote area has a piping size problem as well and has been marked on the plans. No tenting has been done yet either. I gave Kennie permision to cover everything but the end garage and entire third floor until revised hydraulic calculations are provided and a tenting inspection is done.
FIR-Aging Inspection5/23/20065/23/20065/23/2006 DONE
DetailsForrest France
Building is still under construction, work in progress.