INSP-Final Inspection | 8/24/2006 | 8/25/2006 | 8/25/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection is satisfactory, one missing escutcheon replaced while on site.
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2006 | 3/7/2006 | 3/7/2006 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed.
|
INSP-Sprinkler Rough-in | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | PART |
Troy Cobbley
|
|
|
B and D third floors are ok to cover. The ceiling has been installed in unit C without a cover inspection for the sprinkler piping. I told the general contractor the ceiling would need to come out for this inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2005 | 11/29/2005 | 11/30/2005 | A | PART |
Forrest France
|
|
|
c/n items have been completed, overhead rough-in is good for cover on the 1st and 2nd floors only, will need to inspect insulation for the 3rd floor prior to cover.
|
INSP-Sprinkler Rough-in | 11/28/2005 | 11/28/2005 | 11/28/2005 | P | CANC |
Forrest France
|
|
|
No time for this inspection today, to be completed tomorrow am.
|
INSP-Sprinkler Rough-in | 10/25/2005 | 10/26/2005 | 10/26/2005 | A | FAIL |
Forrest France
|
|
|
Install two missing DP at garages, provide hangers for two DP in south garage, provide sprinkler coverage under open space below stairs 2nd floor, provide adequate clearance for pipe in metal vent for fireplace 2nd floor, a head is required in the master closet 3rd floor as it exceeds 24 sq. ft., an inspection for insulation installation protection for cold cavity areas is required prior to final cover per note #35, be aware of possible light fixture obstructions in some locations.
|