INSP-Final Inspection | 4/11/2006 | 4/11/2006 | 4/11/2006 | P | PASS |
Forrest France
|
|
|
Required corrections are complete, permit finaled.
|
INSP-Final Inspection | 4/10/2006 | 4/11/2006 | 4/11/2006 | A | NR |
Forrest France
|
|
|
Permit not ready for final pending project related alarm work.
|
INSP-Final Inspection | 3/31/2006 | 4/3/2006 | 4/3/2006 | A | PART |
Forrest France
|
|
|
Heads blocked by surface mounted lights have been moved, some escutcheons are not installed, performed forward flow, final pending testing of sprinkler related alarms and supervisory conditions.
|
INSP-Final Inspection | 3/30/2006 | 3/30/2006 | 3/30/2006 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler heads are blocked by light fixtures. Heads need to be atleast 20" away from side of fixture. No other items inspected.
|
INSP-Sprinkler Rough-in | 11/3/2005 | 11/3/2005 | 11/3/2005 | P | PART |
Forrest France
|
|
|
Insulation tenting at 3rd floor is acceptable, okay to cover, "blown in" insulation to be done after lid is sheetrocked.
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2005 | 10/6/2005 | 10/6/2005 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed inspection.
|
INSP-Sprinkler Rough-in | 10/3/2005 | 10/3/2005 | 10/3/2005 | P | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover on the 1st and 2nd floors only, a head is required in the 3rd floor master closet as it exceeds 24 sq ft, need to inspect tenting and insulation on the 3rd floor when installed before cover, heads at furnace/water heater need appropriate temp. rating.
|