Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR05-00425
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 495 S CAPITOL BLVD
Project NameBODO BLDG #8- SPR OH HAMPTON
Customer Number 
ePlanReview 
Description
BODO BUILDING #8 - HAMPTON INNS HOTEL - To install complete fire sprinkler protection consisting of: Floor zoned Wet systems, Floor zoned Dry systems, 1000 gpm @ 180 psi Diesel Booster Fire Pump, Class 1 Automatic Standpipe system and a Secondary Water Supply system in a new 235,965-ft/2, eleven story high rise. This building is being constructed of concrete and steel frame for retail, parking and hotel shell. The first floor will contain 7,775-ft/2 of retail space, 9,000-ft/2 of hotel lobby space and 19,020-ft/2 of parking garage space (totaling 35,795-ft/2). The second, third and fourth floors will be parking garage (34,750-ft/2 each floor, totaling 104,250-ft/2). The fifth floor will contain hotel rooms, laundry, meeting rooms, exercise room and an indoor swimming pool (16,000-ft/2). The sixth through eleventh floors will contain hotel guest rooms (13,320-ft/2 per floor, totaling 79,920-ft/2). This submittal is designed for finished and not for a shell permit, except for the 1st floor retail. Separate fire alarm permits will be needed to finish those 1st floor retail spaces. All construction per the approved plans and attached comment list. The fire sprinkler system is being used for area increase. All fire sprinkler and standpipe work shall comply with the IFC 2000, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The underground fire service supply was installed separately under FIR05-00039. This fire permit is attached to building permit: BLD04-01324. This is a shell and core permit only. Separate tenant improvement permits are required to finish this building for occupancy.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/13/20072/14/20072/14/2007APASS
DetailsTroy Cobbley
permit finaled. The last item on Dennis's correction notice, which was the head box has been corrected.
INSP-Final Inspection2/2/20072/2/20072/2/2007PPART
DetailsForrest France
Signed temporary occupancy pending completion of correction notice.
INSP-Sprinkler Rough-in/Hydro1/31/20072/1/20072/1/2007APART
DetailsForrest France
Air test for the 4th floor dry system passed with a max. allowable drop of 1 1/2 psi. over 24 hrs. Noted two locations with wet ceiling tile at the head.
INSP-Sprinkler Rough-in/Hydro1/30/20071/31/20071/31/2007APART
DetailsForrest France
Begin 24 hr. air test of the 4th floor dry system at 49psi.@9:35 am.
INSP-Sprinkler Rough-in/Hydro1/29/20071/30/20071/30/2007APART
DetailsForrest France
OH hydrostatic test for the 4th floor dry system passed inspection.
INSP-Sprinkler Rough-in/Hydro1/29/20071/29/20071/29/2007PPART
DetailsForrest France
Mechanical room hydrostatic test and the conclusion of the tank hydro both completed satisfactory.
INSP-Sprinkler Rough-in1/29/20071/30/20071/29/2007ACANC
DetailsForrest France
Contact: Chris
Hydro - Mechanical Room Phone #: ###-#### Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro1/29/20071/30/20071/29/2007ACANC
DetailsForrest France
Contact: Chris
Hydro 4th floor Phone #: ###-#### Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro1/26/20071/26/20071/26/2007PPART
DetailsForrest France
Begin 72 hr. tank hydro test @ 2:40 pm (37" to water line).
INSP-Sprinkler Rough-in/Hydro1/23/20071/25/20071/26/2007APART
DetailsForrest France
Completed fire pump field acceptance test including pump curve, flow testing, controller operation, engine drive, and jockey pump. Noted some items in need of revision including removal of the ball valves in the pressure sensing lines (NFPA 20 12.5.2.1.6 B3), the exhaust pipe shall be covered or insulated per 11.5.3.3, repair the leak in the 1/2" cooling line at the engine, provide missing stop button at the controller. Also completed acceptable standpipe flow testing via fire pump and FD pumper vehicle.
INSP-Sprinkler Rough-in1/22/20071/23/20071/23/2007ACANC
DetailsTroy Cobbley
elisha; Phone #: ###-#### Internet Inspection Request from: Victoria Beall Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in11/28/200611/29/200611/29/2006PPART
DetailsForrest France
Overhead fire sprinkler is good for cover at the drop ceiling areas on the 4th floor as the required corrections have been verified for compliance.
INSP-Sprinkler Rough-in11/27/200611/28/200611/28/2006AFAIL
DetailsForrest France
Inspection for the 4th floor drop ceiling-heads are overspaced at locations as marked on approved plans, heads at two locations are not installed, heads are shadowed by structural beams which are not indicated on plan set and create obstruction issues.
INSP-Sprinkler Rough-in11/15/200611/16/200611/16/2006APART
DetailsForrest France
Retest of the OH hydrostatic for the 6th floor passed inspeciton.
INSP-Sprinkler Rough-in11/13/200611/13/200611/14/2006PPART
DetailsForrest France
OH hydrostatic test of floors 5 and 7-10 completed satisfactory. The 6th floor failed due to a broken guage.
INSP-Sprinkler Rough-in/Hydro11/7/200611/8/200611/8/2006APART
DetailsForrest France
OH hydrostatic test of the 11th floor is acceptable.
INSP-Sprinkler Rough-in10/19/200610/20/200610/20/2006APART
DetailsForrest France
Piping in the pool room 5th floor matches plans provided, calcs for this remote area to be verified by plan reviewer at resubmittal.
INSP-Sprinkler Rough-in10/9/200610/10/200610/10/2006PFAIL
DetailsTroy Cobbley
Inspection was for the pool room. Two additional branchlines have been added at each end of the pool room. One of them is in the remote area and has been piped off of the 1 1/4" branchline. The starter pieces are now 1 1/4" instead of 1". Plans and calcs need to be resubmitted. Do not cover piping.
INSP-Sprinkler Rough-in9/26/20069/27/20069/27/2006APART
DetailsForrest France
OH rough-in at the drop ceiling areas for the 5th floor corridors and pool room are good for cover, 11th floor corridor drop ceiling is also acceptable for cover.
INSP-Sprinkler Rough-in/Hydro9/18/20069/18/20069/18/2006PPART
DetailsForrest France
10th floor corridor is okay for cover at the drop ceiling areas, noted lacking proper coverage at the far corner of the electrical room, two heads are overspaced at the north end of the main corridor, discussed coverage at the elevator lobby on the 9th floor.
INSP-Sprinkler Rough-in/Hydro9/6/20069/7/20069/7/2006APART
DetailsForrest France
9th floor is good for cover at the drop ceiling areas in the corridor, noted one location at the electrical room which is lacking coverage. 10th floor corridor is not ready for cover inspection at this time.
INSP-Sprinkler Rough-in/Hydro8/31/20068/31/20069/1/2006PPART
DetailsForrest France
Drop ceiling areas in the confrence rooms, adjacent to the pool, and SE of stairs are okay to cover. Noted two overspaced heads in in the public restrooms.
INSP-Sprinkler Rough-in/Hydro8/28/20068/28/20068/28/2006PPART
DetailsForrest France
8th floor corridor fire sprinklers are good for cover.
INSP-Sprinkler Rough-in/Hydro8/21/20068/21/20068/21/2006PPART
DetailsForrest France
5th floor confrence rooms at the drop ceiling areas are good for cover.
INSP-Sprinkler Rough-in/Hydro8/16/20068/16/20068/16/2006PPASS
DetailsTroy Cobbley
The sprinkler piping in the remaining guest room on the 11th floor is ok to cover.
INSP-Sprinkler Rough-in/Hydro8/10/20068/11/20068/11/2006APART
DetailsForrest France
8th and 9th floor guest room adjacent to the temp. elevator are good for cover.
INSP-Sprinkler Rough-in/Hydro8/8/20068/9/20068/10/2006PPART
DetailsForrest France
7th floor guest room rough-in and items from previous c/n on this floor are complete.
INSP-Sprinkler Rough-in/Hydro8/2/20068/3/20068/3/2006PPART
DetailsForrest France
OH inspection for cover at the drop ceiling areas in the 1st floor hotel lobby are good for cover- noted corrections at this location have been completed, noted one sw at garage door west side is too low as installed. Also inspected 6th floor guest room adjacent to temp elevator for rough-in.
INSP-Sprinkler Rough-in/Hydro7/31/20067/31/20068/1/2006PPART
DetailsForrest France
OH rough-in at the hotel lobby drop ceiling areas as noted are okay to cover, two heads in the hard lid above reception counter do not meet min. spacing req.
INSP-Sprinkler Rough-in/Hydro7/27/20067/28/20067/28/2006PFAIL
DetailsForrest France
Inspection for cover at the drop ceiling areas in the lobby first floor failed due to architectural changes not shown on sprinkler plans which affect layout, significant field changes in head location from approved plans, lacking proper coverage at some locations. Submit approved plans reflecting changes and revised sprinkler head locaitons prior to next inspection for cover at this area.
INSP-Sprinkler Rough-in/Hydro7/20/20067/20/20067/21/2006PPART
DetailsForrest France
Noted defficiencies from previous inspection on the 5th floor have been corrected.
INSP-Sprinkler Rough-in/Hydro7/13/20067/14/20067/14/2006PPASS
DetailsTroy Cobbley
The two heads and associated piping located in the first floor elevator lobby are ok to cover.
INSP-Sprinkler Rough-in/Hydro7/12/20067/12/20067/12/2006PPART
DetailsTroy Cobbley
5th Floor piping is ok to cover except for the areas as marked on the plans which need correcting.
INSP-Sprinkler Rough-in/Hydro7/12/20067/12/20067/12/2006PCANC
DetailsForrest France
Contact: Fred; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro6/29/20066/30/20066/30/2006APART
DetailsForrest France
OH rough-in for the 11th floor is acceptable for cover at the hard lid areas.
INSP-Sprinkler Rough-in/Hydro6/27/20066/29/20066/29/2006PPART
DetailsForrest France
Cover inspection for the hotel lobby hard lid entry area is good for cover.
INSP-Sprinkler Rough-in/Hydro6/5/20066/6/20066/7/2006APART
DetailsForrest France
Overhead inspection for the 1st floor hotel lobby soffits, 9th floor main, 10th and 11th floors performed today. The 1st floor soffits are okay to cover-corrections have been completed, 9th floor is acceptable to cover, 10th floor installation is okay-still need to fire caulk wall penetrations prior to cover. The 11th floor failed due to missing EQ brace, overspaced heads at three locations, missing upright at SE stair landing.
INSP-Sprinkler Rough-in/Hydro6/2/20066/2/20066/5/2006PFAIL
DetailsForrest France
Overhead inspection performed for the 1st floor hard lid soffit areas at the hotel lobby-some areas are overspaced, heads not roughed in as shown on plans, be aware of obstructions by adjacent soffits to to higher drop ceiling areas. Also inspected the 9th floor rough-in, installation appears acceptable except for the west main which is still concealed by sheetrock lids- this area will need to be exposed for inspection before approval for cover can be granted for the 9th floor.
INSP-Sprinkler Rough-in/Hydro5/31/20066/1/20066/1/2006AFAIL
DetailsForrest France
Overhead rough-in inspection for cover at the 9th floor failed due to nearly all the piping having been concealed above the ceiling by sheetrock hard lids previous to inspection. No inspection could be performed, notified general contractor of the need to expose the pipe for viewing prior to next inspection request. See note #255 on fire code plan review.
INSP-Sprinkler Rough-in/Hydro5/30/20065/31/20065/31/2006ACANC
DetailsTroy Cobbley
Contact: Fred; Phone #: ###-#### I called listed phone number twice and left two messages. No inspection performed. Will need to be rescheduled.
INSP-Sprinkler Rough-in/Hydro5/12/20065/15/20065/15/2006AFAIL
DetailsForrest France
One pendent head in a soffit at a south guest room is overspaced, missing a lateral EQ brace at the end of SW main, need to provide stamped plans showing field modifications at next inspection, all remaining areas on the 8th floor are acceptable for rough-in cover except as noted.
INSP-Sprinkler Rough-in/Hydro4/28/20065/1/20065/1/2006APART
DetailsForrest France
Overhead fire sprinkler rough-in for the 7th floor is good for cover, need to relocate two overspaced uprights at the SE stair landing, one pendent in SW guest room is overspaced, need to provide approved plans showing design changes and added heads at guest room soffits.
INSP-Sprinkler Rough-in/Hydro4/13/20064/14/20064/14/2006APART
DetailsForrest France
6th floor cover inspection related to the fire sprinklers at the hard lid areas is acceptable.
INSP-Sprinkler Rough-in/Hydro4/7/20064/10/20064/10/2006APART
DetailsForrest France
Overhead rough-in inspection for the 6th floor is good for cover at the hard lid areas as discussed, items addressed include missing 4-way EQ brace, blocked ssu at south stair #1, fire caulking not complete in some areas, added lines in guest room soffits must be shown on plan, be aware of possible light fixture and soffit obstructions, some SW heads are not cut in at this time, laundry chute head is not piped.
INSP-Sprinkler Rough-in/Hydro3/20/20063/21/20063/21/2006PPART
DetailsForrest France
Standpipe flow test performed satisfactory with the required flow and residual pressure required.
INSP-Final Inspection3/13/20063/13/20063/13/2006PFAIL
DetailsForrest France
Provide functional alarm pressure switch at the third floor dry system, repair air compressor at the third floor, provide annual tags on risers, repair stop button at pump controller, secure drum drip assemblies to structure, perform final walkthrough for dry systems code compliance.
INSP-Final Inspection3/8/20063/10/20063/10/2006PFAIL
DetailsForrest France
Standpipe flow test failed to supply the required flow and residual pressure needed. Some c/n items related to the fire pump inspected including test of low fuel supervision device, aux. tank valves have been installed, lock provided on fuel line, heads above aux. tank. Still need flow performance curve data, missing stop button, tags on risers, dry system air compressors set, perform the remainder of alarm testing related to fire sprinkler systems.
INSP-Sprinkler Rough-in/Hydro3/8/20063/10/20063/10/2006APART
DetailsForrest France
Two hour hydrostatic test for the standpipes in stairwells one and two passed inspection.
INSP-Sprinkler Rough-in/Hydro3/3/20063/9/20063/9/2006AFAIL
DetailsForrest France
Several c/n items from the previous day's inspections have not been completed including installation of the aux. tank valves, lock at the fuel line valve, repaired stop button at controller, flow chart data, controller monitoring of fuel levels per NFPA 20 2003 11.4.5.7 and 12.4.1.3 (11). Need to finish branch line above the tank at mech. room, install heads with wrench and NFPA 25 in the head box, install air compressors and re-set dry system air values, installation/inspection tags on the riser.
INSP-Sprinkler Rough-in/Hydro3/8/20063/9/20063/9/2006PFAIL
DetailsForrest France
Hydrostatic test of the standpipes in stair 1 and 2 failed due to pressures below 200 psi at several levels.
INSP-Sprinkler Rough-in/Hydro3/7/20063/8/20063/9/2006PPART
DetailsForrest France
Acceptance test for the fire pump is partially completed, need to verify controller supervisory conditions including overspeed, overtemp, battery charger failure, low fuel, engine trouble, items on review note 31, replace casing drain line with non-corrosive pipe, replace broken controller stop button, install valving to the auxillary tank, lock fuel line valve open, supply performance flow charts for verification, still need to perform the tank suction test, churn psi is above the working pressure limits of the system. Flow test, starts/stops, controller settings, run time, battery switching, rpm, prv have been tested.
INSP-Sprinkler Rough-in/Hydro3/6/20063/8/20063/9/2006AFAIL
DetailsForrest France
Standpipe flow test performed today did not include all required points of flow for testing approval (only the northwest stair tower at parking garage level 4 was tested).
INSP-Final Inspection3/3/20063/10/20063/8/2006ACANC
DetailsForrest France
Contact Charles - TOC inspection; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro3/6/20063/7/20063/8/2006PFAIL
DetailsForrest France
Items lacking for pump test approval include verification of flow test performance curve data, jockey pump controller repair, all items required per NFPA 20 for acceptance testing including a pump mfg. representative who shall be present for the field test (NFPA 20 2003 14.2.1).
INSP-Sprinkler Rough-in/Hydro3/3/20063/7/20063/7/2006APART
DetailsForrest France
Witnessed trip test functionality only (no alarm) of the 2nd and 1st floor dry systems, the air pressure may need to be adjusted per recommendation in manufacturer data sheets, the automatic air compressors must meet requirements of NFPA 13 7.2.6.6.
INSP-Sprinkler Rough-in/Hydro3/6/20063/6/20063/6/2006PPASS
DetailsTroy Cobbley
200lb hydro on the 1st floor wet system passed. 3rd floor dry system trip test passed at 1:30 seconds(less than 500gallons). 1st floor dry system 24 hour air test started at 11:30 with approx. 45psi showing on the guage.
INSP-Conference3/2/20063/6/20063/6/2006ADONE
DetailsForrest France
Contractor called in the wrong permit number, was intended for a BLD life safety confrence to discuss fire code review notes with respect to a temp. occupancy request for the parking garage.
INSP-Sprinkler Rough-in/Hydro3/1/20063/2/20063/2/2006APASS
DetailsTroy Cobbley
200 LB hydro Test on 1st Flr dry System passed.
INSP-Sprinkler Rough-in/Hydro2/28/20062/28/20062/28/2006PPART
DetailsForrest France
Hydrostatic test for the standpipe completed for the north and southwest stair towers, not all portions of the standpipe tested at this time.
INSP-Sprinkler Rough-in/Hydro2/17/20062/17/20062/17/2006APART
DetailsForrest France
24 hour air test of the 2nd floor dry system passed.
INSP-Sprinkler Rough-in/Hydro2/15/20062/16/20062/17/2006AFAIL
DetailsForrest France
Today's inspection was for the 1st floor shell wet system at the north and east perimeter areas for future TI spaces and the start of the 24 hr. air test for 2nd floor dry system, one branch line is overspaced at the south end from a wall as noted on plans, heads in the pump room must be properly spaced for 130ft/2, changes in branch line routing at the electrical room to be shown on resubmittals with all other field changes on this floor, two TI spaces facing Broad St. have been completed prior to shell inspection at these locations, discussed hydro testing requirements for the first floor partial areas, began the 24 hr. air test of the 2nd floor dry system at 10:30 @ 43psi.
INSP-Sprinkler Rough-in/Hydro1/25/20061/26/20061/26/2006PCANC
DetailsForrest France
Inspection for the fire pump flow test canceled due to lack of approved plans for the pump and the associated secondary supply tank approvals.
INSP-Sprinkler Rough-in/Hydro1/25/20061/25/20061/25/2006PNR
DetailsForrest France
Contractor intended inspection to be performed on 1/26 in the pm per telephone conversation.
INSP-Sprinkler Rough-in/Hydro1/10/20061/10/20061/10/2006ADEFR
DetailsForrest France
Duplicate inspection request for hydro completed on 1/9.
INSP-Sprinkler Rough-in/Hydro1/6/20061/9/20061/10/2006APART
DetailsForrest France
Overhead hydrostatic test for the dry systems on levels 2, 3 and 4 passed inspection.
INSP-Sprinkler Rough-in/Hydro12/29/200512/30/200512/30/2005APART
DetailsForrest France
3rd and 4th level parking garage dry system 24 hr air test passed, discussed UG flush and testing schedule for next week.
INSP-Sprinkler Rough-in/Hydro12/28/200512/29/200512/29/2005PFAIL
DetailsForrest France
Air test failed, some items on rough-in c/n for the dry garage systems not complete including two EQ braces, high temp head, branch lines not installed, hanger, listing for valves at one drum drip.
INSP-Sprinkler Rough-in/Hydro12/27/200512/28/200512/28/2005PPART
DetailsForrest France
Inspected dry system overhead at 1st floor, begin 24hr air test of 2nd and 3rd floors dry systems at 47psi each, missing two lines under HVAC 1st floor dry system.
INSP-Sprinkler Rough-in/Hydro12/16/200512/19/200512/19/2005AFAIL
DetailsForrest France
See approved plans for areas defficient including spacing, non-listed valves, coated heads, seismic bracing, signs, missing inspectors test, hanger issues, and areas not inspected at this time-todays inspection was for rough-in at 2nd, 3rd, 4th, floors parking garage dry systems and 1st floor 6" main in soffit. 6" main in the 1st floor soffit is okay to cover except at one lateral brace next to mech. room.