Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR05-00523
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 247 N MILWAUKEE ST
Project NameSPR JARED GALLERIA OF JEWELRY
Customer Number 
ePlanReview 
Description
(JARED THE GALLERIA OF JEWELRY) To remove all Central Model "A" 5.6 K-factor standard spray standard response SSP's and install 69 Tyco Series "TY-FRB," Q.R., SSP, 8.0 K-factor, in the existing remodel of a 7,013-ft/2 retail sales building (6,015-ft/2 ground floor and 998-ft/2 mezzanine) for a new retail jewelry store. The existing yard P.I.V. will be removed and a new W.P.I.V. will be installed which includes system riser modifications. The fire sprinkler work is related to include interior nonbearing walls and suspended ceiling. The upright 5.6 K-factor, standard spray standard response sprinkler will remain. This building is fully fire sprinklered. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD05-01455.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/16/200511/17/200511/17/2005PPASS
DetailsTroy Cobbley
Fire sprinkler finaled
INSP-Final Inspection11/14/200511/15/200511/15/2005AFAIL
DetailsTroy Cobbley
Provide 200 degree pendant at main entrance that is next to the supply grill.
INSP-Sprinkler Rough-in11/9/200511/10/200511/10/2005ACANC
DetailsTroy Cobbley
no time for inspection
INSP-Final Inspection11/9/200511/10/200511/10/2005ACANC
DetailsTroy Cobbley
no time for inspection
INSP-Sprinkler Rough-in/Hydro11/3/200511/4/200511/4/2005APASS
DetailsTroy Cobbley
Anti-freeze hydro test passed.
INSP-Sprinkler Rough-in/Hydro11/2/200511/3/200511/3/2005AFAIL
DetailsTroy Cobbley
Anti-freeze loop hydro test failed twice today.
INSP-Final Inspection11/1/200511/2/200511/3/2005PCANC
DetailsTroy Cobbley
jim paige; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
INSP-Sprinkler Rough-in/Hydro11/1/200511/2/200511/2/2005ACANC
DetailsTroy Cobbley
Canceled hydro since anti-freeze system would hold 200lbs.
INSP-Sprinkler Rough-in/Hydro10/18/200510/19/200510/19/2005APASS
DetailsTroy Cobbley
Overhead hydro test passed.
INSP-Sprinkler Rough-in10/17/200510/18/200510/18/2005APASS
DetailsTroy Cobbley
Piping above the lay-in ceiling tiles is ok to cover except for the new anti-freeze system piping which has not been approved yet. Also the restrooms in the southwest corner are not to be covered until the new uprigth sprinklers are inspected.
INSP-Sprinkler Rough-in/Hydro9/15/20059/16/20059/16/2005PPART
DetailsTroy Cobbley
Hard lid areas as marked on the plans are ok to cover.