INSP-Final Inspection | 12/5/2005 | 12/5/2005 | 12/5/2005 | A | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/2/2005 | 12/5/2005 | 12/5/2005 | A | PASS |
Forrest France
|
|
|
Resubmittals have been reviewed and verified, c/n items are complete, fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | PART |
Forrest France
|
|
|
Approval pending resubmittals reflecting the required changes.
|
INSP-Final Inspection | 11/9/2005 | 11/10/2005 | 11/10/2005 | A | FAIL |
Troy Cobbley
|
|
|
Resubmittals not approved yet. No inspection performed.
|
INSP-Final Inspection | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | FAIL |
Forrest France
|
|
|
Provide resubmittals reflecting items 1 thru 9 on plan review notes, attatched outside mechanical room is not shown on plans, missing longitudinal brace on 21/2 " main, need 200 degree head in upstairs mech room and janitors room 1st floor, install relief valve at riser, need 911 sign, install head cage at SW in mech room, not all items reviewed at this time.
|
INSP-Final Inspection | 10/28/2005 | 10/31/2005 | 10/31/2005 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed inspection.
|
INSP-Supply line flush | 10/17/2005 | 10/18/2005 | 10/18/2005 | A | PART |
Forrest France
|
|
|
Underground fire supply line flush is satisfactory.
|