INSP-Final Inspection | 3/10/2006 | 3/13/2006 | 3/13/2006 | A | PASS |
Forrest France
|
|
|
Shell alarm permit is complete, TI alarm finaled.
|
INSP-Final Inspection | 2/27/2006 | 2/28/2006 | 2/28/2006 | P | PART |
Forrest France
|
|
|
c/n items are complete, final pending shell alarm permit final.
|
INSP-Final Inspection | 2/3/2006 | 2/6/2006 | 2/6/2006 | A | DEFR |
Forrest France
|
|
|
Require approved resubmitted plans for the AHU addresses and changed av location for verification prior to final.
|
INSP-Final Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | P | NR |
Forrest France
|
|
|
Pending shell life safety, sprinkler and alarm permit approvals prior to TI finals.
|
INSP-Final Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | P | PART |
Forrest France
|
|
|
Temp occupancy approval per D.Hanneman pending resubmittals reflecting changes.
|
INSP-Alarm Testing | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | PART |
Forrest France
|
|
|
Devices tested satisfactory, final pending resubmittals for relocated av and address changes on duct detectors.
|
INSP-Sprinkler Rough-in | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | FAIL |
Forrest France
|
|
|
AHU #1 and #2 do not match approved plan with respect to location and addressing, AV at back wall adjacent to registers is obstructed by clothing racks, AHU #3 detector needs to be relocated as discussed, provide resubmittals reflecting the required changes.
|
INSP-Alarm Testing | 10/24/2005 | 10/24/2005 | 10/24/2005 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 10/24/2005 at 8:01:03 AM. Contact: ###-####. cancel
|