INSP-Final Inspection | 3/29/2006 | 3/29/2006 | 3/29/2006 | P | PASS |
Forrest France
|
|
|
Outstanding items have been completed, fire sprinkler finaled.
|
INSP-Final Inspection | 3/24/2006 | 3/27/2006 | 3/27/2006 | A | NR |
Forrest France
|
|
|
The underground supply line is not activated at this time.
|
INSP-Final Inspection | 3/23/2006 | 3/24/2006 | 3/24/2006 | P | FAIL |
Forrest France
|
|
|
Need to complete c/n items, perform forward flow, certify backflow preventer, provide mfg. data sheet for the expansion tank listing for fire protection service, test related alarms.
|
INSP-Sprinkler Rough-in/Hydro | 3/23/2006 | 3/24/2006 | 3/24/2006 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test for the wet and antifreeze systems is satisfactory, one row of heads in the charging room is too low, need to certifiy the backflow, perform forward flow test.
|
INSP-Sprinkler Rough-in | 1/31/2006 | 2/1/2006 | 2/1/2006 | A | FAIL |
Forrest France
|
|
|
One head in the mechanical room is blocked by close proximity to a unistrut support, the hose stations are not installed at this time, heads on the branch lines at exterior covered canopies need minor adjustment with respect to the deflector orientation and pitch of roof, the FDC is poorly located (partially obstructed by adjacent stairs, handrails, and door when in the open position) see review notes for comments and NFPA 13 8.16.2.4.6, IFC 508.5.4, IFC 903.3.7 for requirements.
|
INSP-Supply line flush | 1/16/2006 | 1/17/2006 | 1/17/2006 | A | CANC |
Troy Cobbley
|
|
|
No time for inspection. Per Brian it will be called in for tomorrow.
|