INSP-Final Inspection | 3/3/2006 | 3/3/2006 | 3/3/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/16/2006 | 2/16/2006 | 2/16/2006 | P | PART |
Forrest France
|
|
|
The following items remain for final, need to provide for requirements of note #24 on plan review comments regarding one hour riser room construction or PIV installation, perform the forward flow test for the backflow prevention device, provide and attatch hydraulic calc. sticker to the riser.
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2006 | 2/10/2006 | 2/10/2006 | A | PART |
Forrest France
|
|
|
Hydrostatic test of the overhead fire sprinkler passed.
|
INSP-Sprinkler Rough-in | 12/2/2005 | 12/5/2005 | 12/5/2005 | A | PART |
Forrest France
|
|
|
Verified the unsprinklered cavity at the west dormer has been completely filled with noncombustible insulation per the exception of NFPA 13 8.14.1.2.7. Overhead rough-in is good for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2005 | 11/18/2005 | 11/18/2005 | P | PART |
Forrest France
|
|
|
Overhead fire sprinkler rough-in is okay to cover pending verification of coverage for the dormer at the west roof that is not currrently protected, also will need to verify no obstructions develop after the insulation is installed at the roof.
|