INSP-Final Inspection | 3/13/2006 | 3/13/2006 | 3/13/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/10/2006 | 3/10/2006 | 3/10/2006 | A | FAIL |
Troy Cobbley
|
|
|
Sidewall sprinkler heads are still over spaced and all of the heads are still taped from the painters.
|
INSP-Sprinkler Rough-in/Hydro | 2/15/2006 | 2/15/2006 | 2/15/2006 | P | FAIL |
Troy Cobbley
|
|
|
Provide support for the two 2" vertical pipes and for the vertical drop to the FDC. The sidewall heads are over spaced from the center beams on both sides and the beam exceeds 8" which requires protection beneath. The above ground hydro test passed.
|
INSP-Final Inspection | 1/9/2006 | 1/9/2006 | 1/9/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hanneman's permission for the church to occupy the new addition so that work can be completed in the existing area.
|
INSP-Sprinkler Rough-in/Hydro | 1/6/2006 | 1/6/2006 | 1/6/2006 | P | PART |
Troy Cobbley
|
|
|
Need to finish sprinkler expansion into the existing areas of the church. Per the structural inspector wall in two rooms will need to be extended to the deck. This may effect sprinkler coverage. I can find no record of a hydro test which will need to be done before the permit is finaled. Forward flush of the backflow preventor passed.
|
INSP-Final Inspection | 1/5/2006 | 1/5/2006 | 1/5/2006 | P | CANC |
Troy Cobbley
|
|
|
No inspection done due to lack of time but did notice water was turned off and tamper switches were not working
|
INSP-Sprinkler Rough-in | 12/7/2005 | 12/8/2005 | 12/8/2005 | A | PART |
Forrest France
|
|
|
Spacing in the narthex has been verified, seismic bracing has been modified as requested, an upright head in the nursery area is still blocked by ductwork as indicated on plans.
|
INSP-Sprinkler Rough-in | 11/16/2005 | 11/17/2005 | 11/18/2005 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover except in the areas where deficiencies have been noted on the city approve plans. Resubmittals of the hydraulic calcs for area #3 are needed since upright heads exceed the 120 maz spacing allowed.
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2005 | 11/15/2005 | 11/15/2005 | P | CANC |
Troy Cobbley
|
|
|
Need plans resubmitted and approved prior to calling in inspections.
|