Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberFIR05-00586
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 8013 -8101 W FAIRVIEW AVE
Project NameSPR SHOPKO PLAZA
Customer Number 
ePlanReview 
Description
MILWAUKEE SHOPPING CENTER - aka SHOPKO PLAZA - CANOPY REMODEL * To install a 6” underground fire service supply and an overhead drypipe system for the remodel and construction of a canopy on an existing strip mall building (8013 to 8101 Fairview Ave). The proposed work does not increase the building floor area. This building is fire sprinklered for building area increase. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-02141
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/15/20068/15/20068/15/2006PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection8/10/20068/14/20068/14/2006AFAIL
DetailsTroy Cobbley
Remove the switch for the air compressor and straighten the dry pendant as discussed. (This activity was added in error so we have changed the case status back to Issued.)
INSP-Sprinkler Rough-in/Hydro4/26/20064/27/20064/27/2006PPART
DetailsTroy Cobbley
Trip Test and Forward Flow passed. Several dry pendants need straightened and the missing canopies replaced. Also missing is the ball drip, data sheets for the general air compressor, the switch for the air compressor blanked off, pressure relief valve installed and other misc. items as marked in red ink on the approval notes. The fire alarm interconnection has not been tested yet either.
INSP-Sprinkler Rough-in/Hydro4/25/20064/26/20064/26/2006APASS
DetailsTroy Cobbley
24 hour air test for the dry pipe system has passed. Air pressure was actually gained due to outside temperature.
INSP-Sprinkler Rough-in/Hydro4/24/20064/25/20064/25/2006PPART
DetailsTroy Cobbley
24 Hr Air Test started at 12:35 with 44 1/2psi showing on the guage.
INSP-Sprinkler Rough-in4/18/20064/19/20064/19/2006PFAIL
DetailsTroy Cobbley
called in wrong permit no final per Troy
INSP-Sprinkler Rough-in4/14/20064/18/20064/19/2006PCANC
DetailsTroy Cobbley
Dave; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
INSP-Sprinkler Rough-in/Hydro4/13/20064/14/20064/14/2006APASS
DetailsTroy Cobbley
Above ground hydro test passed.
INSP-Sprinkler Rough-in/Hydro4/10/20064/10/20064/10/2006PNR
DetailsForrest France
Per phone conversation with contractor, project is not ready for a hydrostatic test at this time as scheduled.
INSP-Supply line flush1/23/20061/24/20061/24/2006PPASS
DetailsTroy Cobbley
Underground supply line flush passed.
INSP-Supply line flush1/20/20061/23/20061/23/2006APART
DetailsTroy Cobbley
Inspection was for the underground hydro test which passed. The flush is to be scheduled for later.
INSP-Sprinkler Rough-in10/17/200510/18/200510/18/2005APART
DetailsTroy Cobbley
The rest of the underground supply piping is ok to cover. The installation of the 6" gate valve and road box will need to be verified when United Water finishes the underground tie-in. I pointed out to the sprinkler contractor that there are concealed combustible spaces throughout the entire canopy system that do not have sprinkler protection and will need addressed prior to finaling the permit. This was not an overhead inspection just underground today.
INSP-Sprinkler Rough-in10/17/200510/17/200510/17/2005PPART
DetailsTroy Cobbley
Underground supply piping is ok to cover from United Waters tie in up thrust block.
INSP-Sprinkler Rough-in/Hydro1/16/20051/18/20061/18/2005APART
DetailsTroy Cobbley
Roughin in general looks ok but per note #7 the plans need to be resubmitted with a 30% increase in the size of the remote area due to the deck slope. This may effect pipe sizing. The only items inspected was the sprinkler piping inside the canopy itself.