INSP-Final Inspection | 4/28/2006 | 4/28/2006 | 4/28/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection, permit finaled.
|
INSP-Final Inspection | 4/24/2006 | 4/24/2006 | 4/24/2006 | P | PART |
Forrest France
|
|
|
Need to remove "construction caps" at the pendent heads in the showers on the 1st floor, install missing escutcheons at some locations.
|
INSP-Final Inspection | 4/17/2006 | 4/18/2006 | 4/18/2006 | P | FAIL |
Forrest France
|
|
|
Stairway sprinklers must be installed per NFPA 13 2002 8.14.3.2.1.
|
INSP-Final Inspection | 4/14/2006 | 4/17/2006 | 4/17/2006 | A | DEFR |
Forrest France
|
|
|
Inspection rescheduled
|
INSP-Sprinkler Rough-in | 4/6/2006 | 4/6/2006 | 4/6/2006 | P | PART |
Forrest France
|
|
|
The 11th floor overhead rough-in is good for cover at the drop ceiling areas.
|
INSP-Sprinkler Rough-in | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | PART |
Forrest France
|
|
|
Performed standpipe flow test as required.
|
INSP-Sprinkler Rough-in | 3/30/2006 | 3/31/2006 | 3/31/2006 | A | PASS |
Troy Cobbley
|
|
|
sprinkler piping in the lower ceilings on the first floor are ok to cover. See city approved plans for locations . The west side lower ceiling has a lower soffit that will require an additional sprinkler head to provide proper coverage. Also marked on plans.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2006 | 3/29/2006 | 3/29/2006 | P | PART |
Forrest France
|
|
|
Hydrostatic test of the overhead wet, antifreeze, and standpipe systems is satisfactory, noted one head at the mezzanine stair landing is painted, head cage is missing at head under mezz ductwork, inspected the 5th and 6th floors for cover, the mech penthouse, 11th floor, and portions of the 1st floor are not inspected for cover at this time, discussed items left for completion at the riser room and final testing including standpipe flow test, forward flow of BFP and related sprinkler alarms.
|
INSP-Sprinkler Rough-in | 3/24/2006 | 3/28/2006 | 3/28/2006 | A | PART |
Forrest France
|
|
|
Pump start-up testing performed with manufacturer rep. including churn, rated and 150 percent capacity, manual and automatic starts and stops, jockey pump, set pressures, event log, min. run time, sensing lines, piping arrangements. Performance testing only, no alarm, trouble or supervised conditions tested at this time.
|
INSP-Sprinkler Rough-in | 3/22/2006 | 3/27/2006 | 3/27/2006 | P | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover on floors 10, 9, 8, and 7. Partial inspection of floor 5 as ceiling grid is not complete. Floor 6 and 11 not ready for cover inspection at this time. Also concluded satisfactory 72 hr hydro test of the UG tanks as water level did not drop.
|
INSP-Sprinkler Rough-in | 3/23/2006 | 3/24/2006 | 3/24/2006 | P | PART |
Forrest France
|
|
|
Begin 72hr test of the water level at the underground storage tanks.
|
INSP-Sprinkler Rough-in | 3/16/2006 | 3/17/2006 | 3/17/2006 | P | PART |
Forrest France
|
|
|
Third and fourth floor overhead rough-in is acceptable for cover.
|
INSP-Sprinkler Rough-in | 3/14/2006 | 3/15/2006 | 3/15/2006 | A | PART |
Forrest France
|
|
|
Core areas including the restrooms,elevator lobby, and janitors closet on the 7th-11th floors inspected for rough-in cover, 2nd and 1st floors rough-in is good for cover, one head in the ATM room is blocked by ductwork, discussed hydro testing schedule.
|
INSP-Supply line flush | 3/13/2006 | 3/14/2006 | 3/14/2006 | A | DEFR |
Forrest France
|
|
|
This inspection request was intended for an UG supply line flush under project related permit FIR05-00395-contractor called in the wrong permit number (for overhead), flush was witnessed and performed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2006 | 3/1/2006 | 3/1/2006 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at the 2nd thru 6th floor core areas including restrooms, elevator lobby, janitors closets, tele rooms and electrical rooms, discussed inspection method for the common floor areas, also inspected corridors and adjacent meeting rooms at the 2nd floor.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2006 | 2/28/2006 | 2/28/2006 | P | CANC |
Forrest France
|
|
|
Inspection to be rescheduled due to time constraints.
|
INSP-Sprinkler Rough-in | 2/13/2006 | 2/14/2006 | 2/14/2006 | A | DONE |
Forrest France
|
|
|
On site confrence to discuss location of the penthouse mechanical room standpipe hose connections.
|
INSP-Sprinkler Rough-in | 2/13/2006 | 2/13/2006 | 2/13/2006 | P | CANC |
Forrest France
|
|
|
Inspection was intended for the UG rough-in under a different permit.
|
INSP-Supply line flush | 2/10/2006 | 2/10/2006 | 2/13/2006 | P | NR |
Forrest France
|
|
|
Per contractor, not ready for inspection, to be rescheduled for next week.
|
INSP-Sprinkler Rough-in | 2/9/2006 | 2/9/2006 | 2/10/2006 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the lining of the tank. Provide access to the interior of the tank for inspection
|
INSP-Sprinkler Rough-in | 2/3/2006 | 2/6/2006 | 2/6/2006 | A | PART |
Forrest France
|
|
|
First floor entry lobby hard lid area inspection only, acceptable to cover at this location only. The 1 1/4 branch line to feed the elevator pit sprinklers has not been installed.
|
INSP-Sprinkler Rough-in | 1/12/2006 | 1/12/2006 | 1/12/2006 | P | PART |
Forrest France
|
|
|
Inspected four restrooms on the first floor for overhead rough-in cover.
|
INSP-Sprinkler Rough-in | 1/4/2006 | 1/4/2006 | 1/4/2006 | P | PART |
Forrest France
|
|
|
Inspection for rough-in at 2nd floor hard lid area, sprinklers at ceiling pocket areas must comply with the requirements of note #137 on plan review documents. The updated approved resubmitted plans are required for future overhead inspection requests.
|