INSP-Final Inspection | 4/6/2009 | 4/6/2009 | 4/6/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the fire alarm permit is approved. This permit needs finaled as well if correction have been made.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2005 | 12/12/2005 | 12/13/2005 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. Corrections made.
|
INSP-Sprinkler Rough-in/Hydro | 11/30/2005 | 12/1/2005 | 12/1/2005 | P | FAIL |
Forrest France
|
|
|
Provide approved EQ attatchment methods for TJI's, upright coverage is blocked at area adjacent to restrooms by ductwork, sheetrock has been installed to full height where not shown, drop ceilings are not complete. The overhead hydro test passed inspection.
|