Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR05-00681
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 755 W FRONT ST Unit: 300
Project NameCOLLIERS INTERNATIONAL BODO 7
Customer Number 
ePlanReview 
Description
(COLLIERS INTERNATIONAL - BODO BLDG #7 - 3RD STORY) This building is fire sprinklered for fire area and to allow the multi-theater complex. To relocate and add for sprinklers for the construction of a 10,130-ft/2 office tenant space located on the 3rd story of "BODO Building #7". The building shell was constructed under permit BLD04-01324 and fire sprinklers installed under FIR05-00372 (uncompleted to date). Fire sprinkler work is related to 2 restrooms, new interior nonbearing walls and new suspended ceilings. All fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD05-02358.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/3/20065/4/20065/4/2006APASS
DetailsForrest France
Overhead fire sprinkler work is satisfactory, permit finaled.
INSP-Final Inspection4/26/20064/26/20064/26/2006PFAIL
DetailsForrest France
Three new offices at the NE corner have been built which have caused sprinklers to be overspaced.
INSP-Final Inspection11/22/200511/22/200511/22/2005PPART
DetailsForrest France
Fire sprinkler work is satisfactory, final pending shell sprinkler final approval.
INSP-Sprinkler Rough-in/Hydro11/16/200511/17/200511/17/2005APART
DetailsForrest France
Overhead hydrostatic test passed.
INSP-Final Inspection11/16/200511/17/200511/17/2005AFAIL
DetailsForrest France
Ceiling tile and escutcheons must be installed and protective caps removed in ALL areas prior to final.
INSP-Sprinkler Rough-in/Hydro11/15/200511/16/200511/16/2005PFAIL
DetailsForrest France
Hydrostatic test not completed due to leakage per contractor.
INSP-Final Inspection11/15/200511/16/200511/16/2005PNR
DetailsForrest France
This permit is not ready for final at this time.
INSP-Sprinkler Rough-in11/15/200511/16/200511/16/2005PFAIL
DetailsForrest France
One head is overspaced as circled on plans, one head is too close to a heat diffuser for the supplied temp rating, need canopies and tile and hydrostatic test pre final.