INSP-Final Inspection | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | PASS |
Forrest France
|
|
|
Overhead fire sprinkler work is satisfactory, permit finaled.
|
INSP-Final Inspection | 4/26/2006 | 4/26/2006 | 4/26/2006 | P | FAIL |
Forrest France
|
|
|
Three new offices at the NE corner have been built which have caused sprinklers to be overspaced.
|
INSP-Final Inspection | 11/22/2005 | 11/22/2005 | 11/22/2005 | P | PART |
Forrest France
|
|
|
Fire sprinkler work is satisfactory, final pending shell sprinkler final approval.
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2005 | 11/17/2005 | 11/17/2005 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed.
|
INSP-Final Inspection | 11/16/2005 | 11/17/2005 | 11/17/2005 | A | FAIL |
Forrest France
|
|
|
Ceiling tile and escutcheons must be installed and protective caps removed in ALL areas prior to final.
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2005 | 11/16/2005 | 11/16/2005 | P | FAIL |
Forrest France
|
|
|
Hydrostatic test not completed due to leakage per contractor.
|
INSP-Final Inspection | 11/15/2005 | 11/16/2005 | 11/16/2005 | P | NR |
Forrest France
|
|
|
This permit is not ready for final at this time.
|
INSP-Sprinkler Rough-in | 11/15/2005 | 11/16/2005 | 11/16/2005 | P | FAIL |
Forrest France
|
|
|
One head is overspaced as circled on plans, one head is too close to a heat diffuser for the supplied temp rating, need canopies and tile and hydrostatic test pre final.
|