Permit Information
Permit NumberFIR05-00695
StatusFinaled
Name PROTEX
Site Address 495 S CAPITOL BLVD
Project NameBODO BLDG #8 - ALM
Customer Number 
ePlanReview 
Description
To provide a required manual fire alarm system and all items required for a high rise, which will include fire department communication, voice/evac, manual pull stations and the Fire Command Center. This permit is to install the fire alarm system for the parking structure only, partial ground floor, to include a 2-hour rated corridor for fire department access to the Fire Command Center, located on the ground floor. Floors 2 and 3 will be completed. Elevator #4, which serves the ground floor to 4th floor only will be installed and in service. The 4th floor will not be utilized at this time for public use.

2/26/2006- Plan Modification. The secondary water source is not available at this time and all required fire alarm monitoring points have been removed from the plans. Only the first floor has been revised. Provide the entire drawing package to the PDS Fire Inspector at time of inspection.

The plans indicate they are for T-3 wireless and include additional fire alarm components for T-3 and Carre's Chocolates. These appliances are not required for this permit.

The building permit BLD04-02876 is to construct a new 235,965 square foot, eleven story high rise, concrete and steel framed retail, parking and hotel shell building. When finished, the first floor will contain 7,775 sq. ft. of retail space, 9,000 sq. ft. of hotel lobby space and 19,020 sq. ft. of parking garage space (total 35,795 sq. ft.). The second, third and fourth floors will be parking garage (34,750 sq. ft. each floor, total of 104,250 sq. ft.). The fifth floor will contain hotel rooms, laundry, meeting rooms, exercise room and indoor swimming pool (16,000 sq. ft.). The sixth through eleventh floors will contain hotel guest rooms (13,320 sq. ft. per floor, total 79,920 sq. ft.). This is a shell permit only. No occupancy is allowed under this permit. A separate tenant improvement permit is required to finish this building for occupancy. All construction per the approved plans and attached comment list. JCM *BODO Building #8 - Hampton Inns Hotel (Shell) -
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/26/20072/26/20072/26/2007PPASS
DetailsForrest France
Correction notice items have been completed and verified per field inspection completed by M.Timmerman. Fire Alarm Permit Finaled.
INSP-Final Inspection2/5/20072/5/20072/5/2007PPART
DetailsForrest France
Final pending c/n items.
INSP-Alarm Testing2/2/20072/2/20072/2/2007PPART
DetailsForrest France
Permit final pending 5 item c/n left on site and discussed with general contractor.
INSP-Alarm Testing1/5/20071/5/20071/5/2007PPART
DetailsForrest France
Correction notice items from previous inspectons for guest rooms and common corridors on floors 6 thru 11 have been verified for completion with the exception of HC guest rooms visible notification appliance synchronization.
INSP-Alarm Testing1/4/20071/4/20071/4/2007PPART
DetailsForrest France
Fire alarm testing completed for the 11th floor guest rooms and common corridors. Three HC accessible rooms have strobe notification devices which are not in synchronization. No testing performed for the elevator lobby, service room, nac panels, or floor control for sprinkler monitoring at this time.
INSP-Alarm Testing1/3/20071/3/20071/3/2007PPART
DetailsForrest France
Inspection completed for the 10th floor guest rooms and common corridor. Strobe notification devices are not yet synchronized on general alarm, non-functional speaker in room 1019 repaired while on site. Guest rooms, manual pulls, SD's, fire dampers tested okay.
INSP-Alarm Testing1/2/20071/2/20071/2/2007PFAIL
DetailsForrest France
Alarm testing for the 9th floor guest rooms and common corridors only completed today. Noted the strobes are not in sync at the HC rooms 911 and 910, also noted the a/v in the 910 restroom is functional on strobe only and did not reset, dampers at two locations did not operate, the SD's in the common corridor failed to initiate a general alarm condition.
INSP-Alarm Testing12/29/200612/29/200612/29/2006PDEFR
DetailsForrest France
Rob ###-#### Note: 9th floor Not enough time available with todays schedule that an entire floor inspeciton could be completed. Inspection rescheduled for next week.
INSP-Alarm Testing12/27/200612/28/200612/28/2006PPART
DetailsForrest France
8th floor FA testing performed today, noted the two HC accessible rooms (810 and 811) have non-functional strobe notification devices upon room smoke detection, door holders at the elevator lobby are not programmed, need visual inspection of dampers at two locations, the remainder of guest rooms and common corridor on this floor tested okay.
INSP-Alarm Testing12/19/200612/20/200612/21/2006APART
DetailsForrest France
Alarm tested satisfactory for the 6th floor guest rooms and common corridor areas. Sprinkler monitoring, elvator lobby, FJ remain to be tested on this floor. Also retested defficiencies on the 7th floor, the added SD in room 728 has not yet been programed, signage is to be provided at the visible "door chime" in the HC accessible room, noted voice evac in the guest rooms does not function on general alarm.
INSP-Final Inspection12/19/200612/19/200612/19/2006PDEFR
DetailsForrest France
No time available to perform this inspection today, rescheduled as discussed with contractor.
INSP-Final Inspection12/13/200612/15/200612/15/2006ACANC
DetailsForrest France
No time available to complete this inspection today.
INSP-Final Inspection12/6/200612/7/200612/7/2006AFAIL
DetailsForrest France
Inspection conducted was for the 7th floor not including the sprinkler monitoring, FJ, and elevator recall. Noted three strobes in the main corridor with incorrect cd, SD in two rooms 728 and 730 are blocked by beams, the HC accessible room strobe notification device must function on general alarm, the "doorbell strobe" device violates IFC 2003 901.4.4.
INSP-Conference8/25/20068/28/20068/28/2006ADONE
DetailsForrest France
On site confrence to discuss notification issues at select locations in the corridor, vending areas, and guest rooms per review comments. Noted a/v locations which may not meet min. code requirements for proper coverage and installation.
INSP-Alarm Testing8/11/20068/11/20068/11/2006PNR
DetailsForrest France
Entry to document the observance of fire alarm wire installation for the hotel guest rooms without and prior to issuance of a FA permit and approved FA plans. Both the electrical contractor and general contractor have been notified that work is to cease until FA plans have been submitted and approved. Also notified contractors a stop work order will be issued Monday 8/14 unless a permit has been issued or pulled wire removed.
INSP-Final Inspection3/16/20063/16/20063/16/2006PPART
DetailsForrest France
Fire alarm for the parking garage 1st, 2nd and 3rd levels ONLY tested acceptable for temporary occupancy request.
INSP-Final Inspection3/10/20063/13/20063/13/2006AFAIL
DetailsForrest France
Third floor alarm pressure switch at the dry system failed to reset, low air at the ground level garage dry system adjusted while on site, signal verification list to be faxed in, requested date on batteries at panel. Tested third, second, ground level garage floors, stair 4 elevator, stair 4 and 3 alarm and notification devices, tested pump room, command center, and fire rated corridor alarm/notification/trouble and supervisory conditions, verified items on previous c/n have been completed for the generator room.
INSP-Alarm Testing3/9/20063/10/20063/10/2006ACANC
DetailsForrest France
inspection scheduled to wrap up garage devices; Phone #: ###-#### Internet Inspection Request from: Terry Owsley Inspection cancelled from web by: Terry Owsley
INSP-Final Inspection3/2/20063/9/20063/9/2006AFAIL
DetailsForrest France
Several monitoring points on the fire sprinkler system are not in condition to be tested including the dry systems (air compressors are not set), wet system flow (drain issues), standpipe tampers (closed for hydro test), need to provide proper SD coverage for the generator room as device is overspaced, provide visual notification in the generator room as the proper dB cannot be acheived, provide notification for the HC parking spot on ground level. No test of the elevator as access not available, FJ in stair 2 is not installed. Partial test only of the ground level alarm system today, plans will require resubmittals reflecting all changes, condition of the job prevents completion of testing for approval.