INSP-Final Inspection | 5/9/2006 | 5/9/2006 | 5/10/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2006 | 5/5/2006 | 5/5/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler corrections have been made, inspection passed.
|
INSP-Final Inspection | 5/4/2006 | 5/4/2006 | 5/4/2006 | P | FAIL |
Forrest France
|
|
|
At the time of inspection (approx. 1:30 pm) the required corrections had not been made.
|
INSP-Final Inspection | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | FAIL |
Forrest France
|
|
|
Need to install ceiling tile and escutcheon at one location, install partition between wall and cooler as discussed, one head at the service counter does not match the temp. and response of the remainder of heads in the fire area.
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2006 | 4/26/2006 | 4/26/2006 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover. Insulation had fallen on the upright sprinkler heads but was repaired as I waited.
|
INSP-Sprinkler Rough-in/Hydro | 3/22/2006 | 3/23/2006 | 3/23/2006 | A | PART |
Troy Cobbley
|
|
|
sprinkler piping in soffits is ok to cover. Plans need to be resubmitted to show this piping in the soffits. Pipe sizing has been increased to allow the heads but installation just does not match plans.
|