INSP-Final Inspection | 12/30/2005 | 12/30/2005 | 12/30/2005 | P | PASS |
Forrest France
|
|
|
Defficient items have been corrected, fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/15/2005 | 12/16/2005 | 12/16/2005 | A | FAIL |
Forrest France
|
|
|
No final until all ceiling tile and escutcheons are installed, rough-in defficiencies include one office supplying three heads off a 1" line, three areas in which heads are too close to heat diffusers for temp. rating installed, possible obstruction in the womens restroom at stall divider, one office in the existing area is currently being used for storage, heads at this location are spaced for light hazard.
|
INSP-Sprinkler Rough-in | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | PART |
Forrest France
|
|
|
Rough-in is acceptable to cover pending approval of field changes on resubmittals, some heads at the north lobby remain to be cut in, heads in the existing areas remain to be changed to quick response.
|