Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR05-00800
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 1097 N CURTIS RD
Project Namealm -ST AL'S -CANCER CARE CNTR
Customer Number 
ePlanReview 
Description
To provide elevator controls (new elevator that serves 1st and 2nd floor only), total notification, required smoke detection in corridors, door release and fire/smoke damper control. 2/13/2006 - A new NAC panel is being provided. The required manual fire alarm system includes HVAC shutdown, fire/smoke damper control, door release and notification throughout.

The associated building permit (BLD 05-02073) is to remodel and upgrade specific portions of the basement, 1st and 2nd floors consisting of an total existing 13,259 sq.ft. area of the building per approved plans. Work includes selective demolition; installation of new elevator serving basement, 1st & 2nd levels; remodel for office, treatment & exam rooms and support areas on 1st & 2nd levels; upgrade of ceilings, interior finishes, millwork, electrical, plumbing, mechanical, sprinkler & alarms systems all per approved plans, notes on plans and all attached documentation and plan reviews of all reviewing agencies. (drs) (ST ALPHONSUS)(CANCER CARE CENTER)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/22/20071/22/20071/22/2007PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection1/18/20071/19/20071/19/2007PFAIL
DetailsTroy Cobbley
Need as-builts and the existing door holders connected to the corridor smoke detectors and shown on the as builts
INSP-Final Inspection7/10/20067/10/20067/10/2006PPART
DetailsTroy Cobbley
The second floor portion of the fire alarm system is passed. Still need to test the connection between the new NAC and the main FACP.
INSP-Final Inspection7/6/20067/7/20067/7/2006AFAIL
DetailsTroy Cobbley
This inspection was for occupancy on the second floor. Before approval for the second floor the manual pull station at the east stairwell needs to be lowered and the smoke detector near the elevator lobby reception desk needs relocated away from the supply grill. I also need a print out of the signals that ADT received and to test the supervision of the new NAC panel on the second floor. First floor will need to be tested and the smoke fire damper on the fifth floor. Elevator recall functioned correctly for the machine room, shaft, first floor and second floor.
FIR-Aging Inspection6/16/20066/16/20066/23/2006 NR
DetailsTroy Cobbley
work is in progress