INSP-Final Inspection | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | PASS |
Forrest France
|
|
|
Permitted scope of sprinkler work is complete, upgrade agreement letter verified for compliance.
|
INSP-Sprinkler Rough-in | 3/14/2006 | 3/14/2006 | 3/14/2006 | P | FAIL |
Forrest France
|
|
|
Pendent heads at the remainder of the vacant floor area have been changed to quick response, however no drop ceiling is installed, heads are at various heights AFF, spacing is irregular, final pending compliance with the upgrade agreement per permit review notes.
|
INSP-Final Inspection | 1/5/2006 | 1/5/2006 | 1/5/2006 | P | PART |
Forrest France
|
|
|
Fire sprinkler work for the TI space is satisfactory, need to verify agreement for the adjacent unoccupied area fire sprinkler upgrade prior to final-see review notes for comments.
|
INSP-Final Inspection | 1/3/2006 | 1/4/2006 | 1/4/2006 | A | PART |
Forrest France
|
|
|
One arm-over in the exit corridor by the SW stairs needs a hanger, per contractor the heads in the corridor to be relocated to center of ceiling tile per request by owner, some escutcheons in the elevator lobby have sheetrock mud on them.
|
INSP-Sprinkler Rough-in | 12/28/2005 | 12/28/2005 | 12/28/2005 | P | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at the drop ceiling areas in the TI space and the hard lid ceiling at the lobby, the corridor and restroom areas not complete at this time.
|