Permit Information
Permit NumberFIR05-00880
StatusFinaled
Name PROTEX
Site Address 1445 W COMMERCE AVE
Project Namealm - HAYDEN BEVERAGE
Customer Number 
ePlanReview 
Description
To upgrade the existing sprinkler monitoring fire alarm system. The required sprinkler monitoring fire alarm system includes HVAC shutdown.

The associated building permit (BLD 05-00775) is to construct a one story Type VB 47,307 sq.ft. warehouse/office addition to existing 82,120 sq.ft. unlimited area warehouse/office. Other work includes interior remodeling in the existing warehouse and office areas, all site improvements, paving and landscaping per approved plans and DRH05-00025. Fire sprinklers are used for the unlimited area. This building must maintain 60 foot open yards on all sides. High piled storage requirements are in accordance with the International Fire Code. Separate plans, engineering and permits are required for storage racks over 8 feet in height. (HAYDEN BEVERAGE-ADDITION)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/6/20073/7/20073/7/2007APASS
DetailsForrest France
Final fire alarm inspection passed, permit finaled.
FIR-Aging Inspection3/6/20073/6/20073/6/2007PDONE
DetailsForrest France
Final inspection scheduled.
INSP-Final Inspection7/12/20067/13/20067/13/2006PFAIL
DetailsTroy Cobbley
Need print out of the signals sent and updated plans showing the additional tamper switches.
INSP-Final Inspection3/8/20063/10/20063/10/2006APART
DetailsForrest France
c/n items have been completed, all items tested except two AHU detectors which are not installed at this time, provide signage on the door to the FACP.
INSP-Final Inspection3/2/20063/6/20063/6/2006APART
DetailsForrest France
7 AHU duct smoke detectors tested okay, 2 AHU detectors are not installed at this time, a ceiling will be required at the riser/FACP room which will require relocation and testing of the SD at the panel, need to test flow switches at the main riser (contractor unable to flow water at this time), tamper switch at antifreeze system point #6 needs adjustment, need to test low air and the WPI tamper at south riser as contractor had not made preparation to do so, provide signage at the door to the FACP.